Project-ending competence in premature project closures

Abstract Project management literature tends to focus on the early phases of a project and on the associated generic project management competences, such as planning, scheduling, budgeting, resourcing and motivating. Only a small fraction of the discussion is devoted to project closure and to the competences needed when a project fails to reach the goals and so needs to be closed prematurely. The purpose of this paper is to develop an understanding of project-ending competences needed in premature project closures. Two cases of premature project closure are analysed in different contexts: in the car industry and the aircraft manufacturing industry. The key findings concern the managerial challenges that are present in premature project closures: the need for involvement of senior and also project managers, the need to understand the often changed role of internal and external project stakeholders, and the need to understand that the ‘future matters’ in premature project closure.

[1]  Lars-Gunnar Mattsson,et al.  Marketing Investments and Market Investments in Industrial Networks , 1985 .

[2]  Anna Lund Jepsen,et al.  Stakeholder analysis in projects: Challenges in using current guidelines in the real world , 2009 .

[3]  Nils O.E. Olsson,et al.  Management of flexibility in projects , 2006 .

[4]  H. Haapasalo,et al.  Project management competence development framework in turbulent business environment , 2006 .

[5]  C. R. Anderson,et al.  Stage of the Product Life Cycle, Business Strategy, and Business Performance , 1984 .

[6]  Anders Söderholm,et al.  A theory of the temporary organization , 1995 .

[7]  Lynn Crawford,et al.  Fundamental uncertainties in projects and the scope of project management , 2006 .

[8]  B MilesMatthew,et al.  Qualitative Data Analysis , 2009, Approaches and Processes of Social Science Research.

[9]  I. Royer Why bad projects are so hard to kill. , 2003, Harvard business review.

[10]  Hans Rämö Doing things right and doing the right things Time and timing in projects , 2002 .

[11]  Liz Lee-Kelley,et al.  The Titanic sunk, so what? Project manager response to unexpected events , 2010 .

[12]  M. Martinsuo,et al.  Supplier integration in complex delivery projects: comparison between different buyer-supplier relationships , 2010, IEEE Engineering Management Review.

[13]  Karlos Artto,et al.  Change decisions in product development projects , 2007 .

[14]  R. Müller,et al.  A Retrospective look at our Evolving Understanding of Project Success , 2005, IEEE Engineering Management Review.

[15]  Virpi Havila,et al.  Managing Project Ending , 2008 .

[16]  Janita F. J. Vos,et al.  Investigating the use of the stakeholder notion in project management literature, a meta-analysis , 2008 .

[17]  Jesper B. Sørensen,et al.  The interplay between theory and method , 2007 .

[18]  P. K. De Project termination practices in Indian industry: a statistical review , 2001 .

[19]  Peter Fredriksson,et al.  Sourcing trends in the car industry - a survey of car manufacturers' and suppliers' strategies and relations , 2002 .

[20]  Jack R. Meredith,et al.  Project Management: A Managerial Approach , 1989 .

[21]  Jonas Söderlund,et al.  DEVELOPING PROJECT COMPETENCE: EMPIRICAL REGULARITIES IN COMPETITIVE PROJECT OPERATIONS , 2005 .

[22]  P. Dawson In at the deep end: Conducting processual research on organisational change , 1997 .

[23]  J. Rodney Turner,et al.  THE HANDBOOK OF PROJECT-BASED MANAGEMENT , 2008 .

[24]  Terje I. Vaaland,et al.  Improving project collaboration: start with the conflicts , 2004 .

[25]  Matti Vartiainen,et al.  Managing knowledge and knowledge competences in projects and project organisations , 2003 .

[26]  Jonas Söderlund,et al.  Relating, reflecting and routinizing: Developing project competence in cooperation with others , 2008 .

[27]  Kirsi Aaltonen,et al.  Project stakeholder analysis as an environmental interpretation process , 2011 .

[28]  Jean Hartley,et al.  Case study research , 2004 .

[29]  Anders Söderholm,et al.  Project management of unexpected events , 2008 .