Simulating Uncertainties in Construction Projects with Chronographical Scheduling Logic

AbstractThe more complex a project, the more attractive nontraditional project delivery methods like design-build or fast-tracking become with these delivery methods and uncertainty has to be explicitly integrated into the network calculations. Uncertainties assess levels of compliance with various constraints. This paper contributes to the existing body of knowledge by modeling diverse types of execution uncertainties, such as construction operation, execution process, and work with doubtful results, and by extending the traditional logic and modeling uncertainties using the chronographic time-scaled, point-to-point relations, production-based dynamic relations, and function dependencies between in-progress activities. The dependencies between activities can be related to the external scale (usually representing time) or an internal scale (usually representing quantity). Using the Monte Carlo simulation, the paper simulates the impact of construction operations, execution processes, and work with doubtfu...

[1]  Steven D. Eppinger,et al.  A Model-Based Framework to Overlap Product Development Activities , 1997 .

[2]  Edmond T. Miresco,et al.  A chronographic method for construction project planning , 2006 .

[3]  Michael R. Duffey,et al.  Statistical dependence in risk analysis for project networks using Monte Carlo methods , 1999 .

[4]  Low Sui Pheng,et al.  Environmental factors and work performance of project managers in the construction industry , 2006 .

[5]  Julio C. Martinez,et al.  State-Based Probabilistic Scheduling Using STROBOSCOPE's CPM Add-On , 1997 .

[6]  Steven D. Eppinger,et al.  Generalised models of design interation using signal flow graphs , 1997 .

[7]  Steven D. Eppinger,et al.  Generalized models of design iteration using signal flow graphs , 1995 .

[8]  K. MacCrimmon,et al.  An Analytical Study of the PERT Assumptions , 1964 .

[9]  D. Gong,et al.  Time-uncertainty analysis in project networks with a new merge-event time-estimation technique , 1993 .

[10]  Jesus M. de la Garza,et al.  Critical Path Method with Multiple Calendars , 2005 .

[11]  Reza H. Ahmadi,et al.  Concurrent Crashing and Overlapping in Product Development , 2004, Oper. Res..

[12]  Miklós Hajdu Network Scheduling Techniques for Construction Project Management , 1996 .

[13]  Feniosky Peña-Mora,et al.  Modeling and representation of non-value adding activities due to errors and changes in design and construction projects , 2007, 2007 Winter Simulation Conference.

[14]  Edmond T. Miresco,et al.  Simulation of scheduling logic using dynamic functions , 2013 .

[15]  J. D. Wiest,et al.  Precedence diagramming method: Some unusual characteristics and their implications for project managers , 1981 .

[16]  Edmond T. Miresco,et al.  Decision Support for Project Management using A Chronographic Approach , 2002, J. Decis. Syst..

[17]  Feniosky Peña-Mora,et al.  Dynamic Planning for Fast-Tracking Building Construction Projects , 2001 .

[18]  Frank E. Grubbs Letter to the Editor---Attempts to Validate Certain PERT Statistics or “Picking on PERT” , 1962 .

[19]  Feniosky Peña-Mora,et al.  DYNAMIC PLANNING AND CONTROL METHODOLOGY FOR DESIGN/BUILD FAST-TRACK CONSTRUCTION PROJECTS , 2001 .

[20]  D. Malcolm,et al.  Application of a Technique for Research and Development Program Evaluation , 1959 .

[21]  Simaan M. AbouRizk,et al.  Simplified CPM/PERT Simulation Model , 2000 .