LDA-Based Model for Measuring Impact of Change Orders in Apartment Projects and Its Application for Prerisk Assessment and Postevaluation

AbstractThis study analyzed the impact of change orders on construction projects by using the loss distribution approach (LDA), which is used in finance to analyze operational risks, and proposed a framework for applying the LDA to construction. It examined 9,028 change orders for 237 apartment housing projects in South Korea. Prior to the analysis, the change-order factors were classified into five categories and the work types into eight categories in order to form a risk matrix. The severity and frequency distributions of each cell were calculated based on the risk matrix. Because the amount of loss can vary depending on the construction cost, severity was defined as the amount of loss relative to the construction cost. Using this, the authors calculated the loss distribution of each cell and combined them to derive the total loss distribution. The analysis results confirmed that field conditions had the largest overall impact on change orders. This was ascribed to the limitations of estimating and ref...

[1]  Ali Touran,et al.  Probabilistic Model for Cost Contingency , 2003 .

[2]  Ting-ya Hsieh,et al.  Statistical analysis of causes for design change in highway construction on Taiwan , 2005 .

[3]  Simaan M. AbouRizk,et al.  Quantitative Method for Updating Cost Contingency throughout Project Execution , 2012 .

[4]  Paolo Giudici,et al.  A statistical method to optimize the combination of internal and external data in operational risk measurement , 2007 .

[5]  Jin-Kyung Lee,et al.  Cost Overrun and Cause in Korean Social Overhead Capital Projects: Roads, Rails, Airports, and Ports , 2008 .

[6]  W. B. Ledbetter,et al.  Causes of Quality Deviations in Design and Construction , 1992 .

[7]  Faisal Manzoor Arain,et al.  Causes of Discrepancies between Design and Construction , 2004 .

[8]  David J. Edwards,et al.  Forensic Project Management: An Exploratory Examination of the Causal Behavior of Design-Induced Rework , 2008, IEEE Transactions on Engineering Management.

[9]  Jieh-Haur Chen,et al.  KNN based knowledge-sharing model for severe change order disputes in construction , 2008 .

[10]  Xianhai Meng,et al.  Taxonomy for change causes and effects in construction projects , 2009 .

[11]  C. William Ibbs Quantitative Impacts of Project Change: Size Issues , 1997 .

[12]  Peter E.D. Love,et al.  Using systems dynamics to better understand change and rework in construction project management systems , 2002 .

[13]  Peter E.D. Love,et al.  Design Error Classification, Causation, and Prevention in Construction Engineering , 2010 .

[14]  Amr A. Oloufa,et al.  Model for Quantifying the Impact of Change Orders on Project Cost for U.S. Roadwork Construction , 2010 .

[15]  Jian Zuo,et al.  Prediction System for Change Management in Construction Project , 2010 .

[16]  Peter E.D. Love,et al.  Design Error Costs in Construction Projects , 2012 .

[17]  A. S. Alnuaimi,et al.  Causes, Effects, Benefits, and Remedies of Change Orders on Public Construction Projects in Oman , 2010 .

[18]  Awad S. Hanna,et al.  Cumulative Effect of Project Changes for Electrical and Mechanical Construction , 2004 .

[19]  David Arditi,et al.  Budgeting Owner's Construction Contingency , 2007 .

[20]  Peter E.D. Love,et al.  Quantifying the causes and costs of rework in construction , 2000 .

[21]  Ian Flood,et al.  Prediction of Financial Contingency for Asphalt Resurfacing Projects using Artificial Neural Networks , 2012 .

[22]  Awad S. Hanna,et al.  Quantitative Definition of Projects Impacted by Change Orders , 2002 .