Construction method of continuously reinforced concrete pavements using reinforcement inducing/fixing equipment

PURPOSE: A continuously reinforced concrete pavement method using reinforcing bar guiding/fixing equipment is provided to automatically arrange longitudinal reinforcing bars on regular positions without lateral auxiliary reinforcing bars, thereby minimizing the amount of reinforcing bars and workloads and improving the construction speed. CONSTITUTION: A continuously reinforced concrete pavement method using reinforcing bar guiding/fixing equipment(100) includes: a step of driving and moving the reinforcing bar guiding/fixing equipment with guide tubes and reinforcing bar holding devices in order to longitudinally arrange the reinforcing bars on regular positions; a step of placing concrete on the upper side of the arranged reinforcing bars; and a step of finishing the placed concrete to be flattened with a paver(300). [Reference numerals] (AA) Driving direction