Towards last planner system implementation in Gaza Strip, Palestine

Abstract The Gaza Strip’s construction industry in Palestine is suffering from the existence of unreliable production plans with great variability. One of the innovative solutions to avoid, eliminate or at least reduce plan variation is the adoption of last planner system (LPS). This research highlights the importance of eliminating plan variation in the production planning and control process in Gaza Strip as a key improvement in the delivery process of construction projects through the use of LPS. This research applies a survey strategy that uses two data collection methods, including questionnaire and interview. The results show that several elements of LPS already exist in Gaza Strip. Nevertheless, these elements do not follow the same approach of LPS. The main challenge is the involvement of many subcontractors. The primary variation cause is the unavailability of materials. The critical success factor is the top management support.

[1]  Olli Seppänen,et al.  IGLC 2016 - 24th Annual Conference of the International Group for Lean Construction , 2016 .

[2]  Julio J. Ochoa,et al.  Reducing plan variations in delivering sustainable building projects , 2014 .

[3]  Scott Fernie,et al.  Making sense of supply chain management: a comparative study of aerospace and construction , 2005 .

[4]  Gregory A. Howell,et al.  Toward construction JIT , 1997 .

[5]  Wallace J. Hopp,et al.  Factory physics : foundations of manufacturing management , 1996 .

[6]  Tammy McConaughy,et al.  Subcontractor Collaboration and Breakdowns in Production: The Effects of Varied Lps Implementation , 2013 .

[7]  Gregory Howell,et al.  Applying Last Planner in the Nigerian Construction Industry , 2012 .

[8]  John Rooke,et al.  An examination of the barriers to last planner implementation , 2011 .

[9]  Iris D. Tommelein,et al.  Pull-Driven Scheduling for Pipe-Spool Installation: Simulation of Lean Construction Technique , 1998 .

[10]  James P. Womack,et al.  Lean Thinking: Banish Waste and Create Wealth in Your Corporation , 1996 .

[11]  Sarel Lavy,et al.  Last Planner System Implementation Challenges , 2010 .

[12]  Adnan Enshassi,et al.  Implementation of Lean Tools on Safety in Construction Projects in Palestine , 2014 .

[13]  Lauri Koskela,et al.  Last Planner and Critical Chain in Construction Management: Comparative Analysis , 2010 .

[14]  Iris D. Tommelein,et al.  Understanding the role of “tasks anticipated” in lookahead planning through simulation , 2015 .

[15]  Albert Sydney Hornby,et al.  Oxford advanced learner\'s dictionary of current English / A S Hornby with A P Cowie, A C Gimson , 1975 .

[16]  기술전략팀 [기술강좌] Last Planner , 2003 .

[17]  Felix Hueber,et al.  Production And Operations Analysis , 2016 .

[18]  Patricia Tzortzopoulos,et al.  Effects of the Interactions Between LPS and BIM on Workflow in Two Building Design Projects , 2014 .

[19]  Fernando Cerveró-Romero,et al.  Last Planner System and Lean Approach Process Experiences From Implementation in Mexico , 2013 .

[20]  Glenn Ballard,et al.  Production Control Principles , 2009 .

[21]  Eduardo Rosas Integrating the Design Structure Matrix and the Last Planner System Into Building Design , 2013 .

[22]  Lauri Koskela,et al.  Improving construction management practice with the Last Planner System: a case study , 2014 .

[23]  Ana Nieto-Morote,et al.  Last Planner Control System Applied to a Chemical Plant Construction , 2012 .

[24]  Rafael Sacks,et al.  Social Network Development in Last Planner System Implementations , 2013 .

[25]  刘江雪,et al.  LIN volume 11 issue 2 Cover and Back matter , 1975, Journal of Linguistics.

[26]  Iris D. Tommelein,et al.  Acknowledging Variability and Uncertainty in Product and Process Development , 2003 .

[27]  Farook Hamzeh,et al.  The Lean Journey: Implementing the Last Planner ® System in Construction , 2011 .

[28]  Kathryn Davies,et al.  Last Planner System – a Step Towards Improving the Productivity of New Zealand Construction , 2013 .

[29]  Usama H. Issa,et al.  Implementation of lean construction techniques for minimizing the risks effect on project construction time , 2013 .

[30]  Sakari Pesonen,et al.  DEFINING THE PATH: A CASE STUDY OF LARGE SCALE IMPLEMENTATION OF LAST PLANNER , 2010 .

[31]  Sui Pheng Low,et al.  The Last Planner System in China's construction industry — A SWOT analysis on implementation , 2014 .

[32]  Philip E. T. Lewis,et al.  Research Methods for Business Students , 2006 .

[33]  Lauri Koskela,et al.  The four roles of supply chain management in construction , 2000 .

[34]  Glenn Ballard,et al.  Management Thinking in the Earned Value Method System and the Last Planner System , 2010 .

[35]  Farook Hamzeh,et al.  Using simulation to study the impact of improving Lookahead planning on the reliability of production planning , 2011, Proceedings of the 2011 Winter Simulation Conference (WSC).

[36]  Gregory A. Howell,et al.  Capacity Utilization and Wait Time: A Primer for Construction , 2001 .

[37]  Christine Pasquire,et al.  The magic of the Last Planner® System for Nigerian construction , 2014 .

[38]  Lauri Koskela,et al.  Ten Years of Last Planner in Finland - Where Are We? , 2012 .

[39]  Carlos T. Formoso,et al.  A SURVEY ON THE LAST PLANNER SYSTEM: IMPACTS AND DIFFICULTIES FOR IMPLEMENTATION IN BRAZILIAN COMPANIES , 2010 .

[40]  Farook Hamzeh,et al.  Improving Construction Workflow- The Role of Production Planning and Control , 2009 .

[41]  Mike Cohn,et al.  Agile Estimating and Planning , 2005 .

[42]  Iris D. Tommelein,et al.  Lean management methods for complex projects , 2012 .

[43]  Marion M. Russell,et al.  Allocation of Time Buffer to Construction Project Task Durations , 2013 .

[44]  Gregory A. Howell,et al.  SHIELDING PRODUCTION: ESSENTIAL STEP IN PRODUCTION CONTROL , 1998 .

[45]  Min Liu,et al.  Using Last Planner and a Risk Assessment Matrix to Reduce Variation in Mechanical Related Construction Tasks , 2012 .

[46]  Antti Leino,et al.  Last Planner and Zero Accidents Program Integration - Workforce Involvement Perspective , 2011 .

[47]  Glenn Ballard,et al.  Lean production theory: Moving beyond "Can-Do" * , 1997 .

[48]  Iris D. Tommelein,et al.  Look-ahead Planning: Screening and Pulling , 1997 .

[49]  Iris D. Tommelein,et al.  More Just-in-Time: Location of Buffers in Structural Steel Supply and Construction Processes , 1999 .

[50]  Herman Glenn Ballard,et al.  THE LAST PLANNER SYSTEM OF PRODUCTION CONTROL , 2000 .

[51]  Taiichi Ohno,et al.  Toyota Production System : Beyond Large-Scale Production , 1988 .

[52]  Greg Howell,et al.  Implementing Lean Construction: Stabilizing Work Flow , 1997 .

[53]  Boaz Ronen,et al.  Critical Chain: A New Project Management Paradigm or Old Wine in New Bottles? , 2005 .

[54]  Subashini Suresh,et al.  A Case Study of Last Planner System Implementation in Nigeria , 2013 .

[55]  Mnk Saunders,et al.  Choosing research participants , 2012 .

[56]  Thais da C. L. Alves,et al.  Last Planner® System Is the Gateway to Lean Behaviors , 2013 .

[57]  Gregory A. Howell,et al.  Interaction between subcycles: one key to improved methods , 1993 .

[58]  Kiyoung Son,et al.  Survey of Motivations, Benefits, and Implementation Challenges of Last Planner System Users , 2013 .

[59]  Farook Hamzeh,et al.  Modeling the Last Planner System Metrics: A Case Study of an Aec Company , 2013 .

[60]  K. London,et al.  An industrial organization economic supply chain approach for the construction industry: a review , 2001 .

[61]  Glenn Ballard,et al.  Implementing lean construction: Reducing inflow variation , 1997 .

[62]  Eduardo L. Isatto,et al.  Simulating the Last Planner With Systems Dynamic , 2010 .

[63]  Glenn Ballard,et al.  The Combination of Last Planner System and Location-Based Management System , 2010 .

[64]  Gregory A. Howell,et al.  Case Studies of the Allocation and Reduction of Time Buffer through Use of the Last Planner System , 2015 .

[65]  Stephen F. Smith,et al.  Is Scheduling a Solved Problem , 2005 .

[66]  Lauri Koskela,et al.  An exploration towards a production theory and its application to construction , 2000 .