Dome load control and crane land path evaluation for Tank 241-SY-101 during hydrogen mitigation pump removal and installation
暂无分享,去创建一个
This report revisits and consolidates two analyses previously performed for the installation of the Hydrogen Mitigation Pump (HMT) pump. The first report determines, as a function of the crane-imposed dome load, the point to which the crane can encroach into the exclusion zone without exceeding the 50-ton limit. The second performs a load evaluation for the crane and the components in the load path (crane lift accessories and pump). In doing so, it determines the weakest component in the load path and the effect of this component on the allowable encroachment distance. Furthermore, the second report sets operational limits on the allowable load decrease (unload) during installation in the event the pump sticks in the riser. The analysis presented here expands on the latter subject by setting an operational limit on the amount of allowable load increase (overload) during pump removal in the event the pump sticks in the riser.