Optimization of limestone sizing for CFB combustors: Results of pilot plant and bench-scale testing
暂无分享,去创建一个
A grant to study the performance of limestones in a Circulating Fluidized Bed Combustor was obtained in 1991 from the Pennsylvania Energy Development Authority (PEDA) by Tampella Power Corporation (TPC). The overall objective of this PEDA project was to carry out a systematic pilot plant tests at TPC`s pilot plant in Williamsport, Pennsylvania, in systematic order to identify ways of improving sulfur capture and limestone utilization through better control of the size distribution and residence time of the limestone particles in the furnace. It was also an objective to determine if bench scale testing could be of value in predicting CFB sorbent behavior. The pilot plant and bench test results were incorporated into an empirical Correlation which accounts for the size distribution and residence time of solids in CFB boiler.