Space Station Freedom contingency reboost and resupply strategies

The objective of this study was to determine the requirements necessary to ensure a viable Space Station Freedom (SSF) in the event of a delay in the date of the first element launch, and/or in the event that the nominal assembly sequence is interrupted, perhaps due to a delay in the Space Shuttle Launch Schedule. Orbit lifetimes, reboost fuel requirements, and controllability requirements were calculated for each stage of the SSF assuming anywhere from a 6 to 24 month delay/interruption in the baseline SSF assembly sequence. These results were assessed in order to formulate strategies to assure SSF viability in the presence of assembly sequence delays and interruptions.