Cost Development Over-time at Construction Planning Phase: Empirical Evidence from Norwegian Construction Projects☆

Abstract Every capital-intensive constructions project goes through various challenges throughout their project life cycle. However, one crucial challenge is to understand and trace cost development over-time at planning phase. The research aim is threefold: firstly, to identify the critical factors of cost development in the planning phase. Secondly, to investigate empirically a dyadic relationship of cost deviation over time and quantitatively chart their developments. Thirdly, to analyze the construction cost data, discuss their cost developments and identify critical projects based on their actual financial impacts. The research considers 110 projects and analyze them using qualitative and quantitative research methods. The results showed higher cost escalation in the planning phase. The research identified critical factors for cost escalations at the planning phase. The average cost escalation of 110 projects (

[1]  Lester A Hoel,et al.  Highway Project Cost Estimating Methods used in the Planning Stage of Project Development , 2001 .

[2]  Knut Samset Projects, Their Quality at Entry and Challenges in the Front-end Phase , 2009 .

[3]  Søren L. Buhl,et al.  What Causes Cost Overrun in Transport Infrastructure Projects? , 2004, 1304.4476.

[4]  Peter Lundman,et al.  Cost management for underground infrastructure projects: a case study on cost increase and its causes , 2011 .

[5]  Guru Prakash Prabhakar,et al.  Culture and Conflict Management Style of International Project Managers , 2009 .

[6]  Alexia A. Nalewaik,et al.  Challenges Reporting Project Costs and Risks to Owner Decisionmakers , 2009 .

[7]  Hans Lind,et al.  Explaining cost overruns in infrastructure projects: a new framework with applications to Sweden , 2014 .

[8]  James Odeck,et al.  Cost overruns in road construction--what are their sizes and determinants? , 2004 .

[9]  David Grau,et al.  Predictability Index: Novel Metric to Assess Cost and Schedule Performance , 2015 .

[10]  Mohammad Barzandeh Accuracy of estimating techniques for predicting residential construction costs – A case study of an Auckland residential construction company , 2011 .

[11]  Akintola Akintoye,et al.  Analysis of factors influencing project cost estimating practice , 2000 .

[12]  Edward J. Jaselskis,et al.  Improving predictability of construction project outcomes through intentional management of indirect construction costs , 2014 .

[13]  Guru Prakash Prabhakar,et al.  Projects and Their Management: A Literature Review , 2009 .

[14]  Geoffrey Qiping Shen,et al.  Factors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construction Projects , 2016 .

[15]  Helena Ellingerová Planning and Management of Construction Budgetary Costs , 2011 .

[16]  B. Flyvbjerg,et al.  Different Cost Performance: Different Determinants? The Case of Cost Overruns in Dutch Transport Infrastructure Projects , 2012, 1307.2179.

[17]  Keith R. Molenaar,et al.  Guidance for Cost Estimation and Management for Highway Projects During Planning, Programming, and Preconstruction , 2006 .