Experimental Study on Secondary System Grounding of UHV Fixed Series Capacitors via EMI Measurement on an Experimental Platform

In isolating the disconnecting switch of ultra-high voltage (UHV) fixed series capacitors (FSCs), electromagnetic-interference (EMI) problems arise on the secondary-side protection and control devices. If the platform-mounted high-potential secondary system is not properly grounded, malfunction or damage to EMI-vulnerable devices may follow. This paper focuses on high-potential measurement and characterization of EMI in the secondary side of UHV FSC. A life-size experimental platform was built at first, and a corresponding high-potential platform-based measurement system was developed. Then, by isolating the disconnect switch in the experimental circuit, the common-mode (CM) voltage, differential-mode (DM) voltage, and current under five different conditions of secondary system grounding were obtained. In addition, EMI characterization was described and analyzed, and statistical distribution was given. Finally, several proposals based on EMI data and characterization were presented to shed light on designing and engineering UHV fixed series capacitors in addressing EMI problems.

[1]  L. Kirschner,et al.  Benefits and design aspects of Sao Joao do Piaui 500 kV series capacitors , 2004, 2004 IEEE/PES Transmision and Distribution Conference and Exposition: Latin America (IEEE Cat. No. 04EX956).

[2]  Bin Han,et al.  Research on power frequency overvoltage of UHV double-circuit transmission system with series compensation , 2010, 2010 International Conference on Power System Technology.

[3]  V. Cooray,et al.  Resistance of Spark Channels , 2006, IEEE Transactions on Plasma Science.

[4]  F.K. Tseng,et al.  Overvoltages on EHV transmission lines due to faults and subsequent bypassing of series capacitors , 1977, IEEE Transactions on Power Apparatus and Systems.

[5]  Fei Gao,et al.  Protection of series compensation station against lightning intruded wave in 1000kV AC transmission system , 2010, 2010 International Conference on Power System Technology.

[6]  Zhao Cheng-nan,et al.  Spark model for 1100kV GIS disconnecting switch , 2011, 2011 1st International Conference on Electric Power Equipment - Switching Technology.

[7]  R. Grunbaum,et al.  Series capacitors facilitate long distance AC power transmission , 2005, 2005 IEEE Russia Power Tech.

[8]  S. E. Wright,et al.  Transient electromagnetic interference in substations , 1994 .

[9]  Yan Xianglian Protection of Series Compensation Station Against Lightning Intruded Wave in 1000 kV AC Transmission System , 2010 .

[10]  Jiawen Yu,et al.  Studies on series compensation of UHV transmission line , 2010, 2010 International Conference on Power System Technology.