Quantitative risk and uncertainty modeling of economic costs and benefits incurred by execution of large projects is usually done by representation of uncertain input variables by probability distributions and subsequent calculation of uncertain output variables by Monte Carlo simulation. This approach is widely recommended in the literature and even by the EU as a guide to handling of large infrastructure investment projects to avoid underestimation of cost and overestimation of benefits. Thus the probabilistic approach is established as a de facto best practice and also a broadly accepted tool among engineers and economists in construction companies and public authorities. At the same time there are an increasing number of reports documenting serious cost overruns and benefit shortfalls as well as ex post results beyond the uncertainty limits predicted by ex ante analysis thereby challenging the relevance and usefulness of the probabilistic approach to modeling of economic project uncertainty. This paper points out some of the weaknesses and pitfalls of the probabilistic modeling approach and explains why it can lead to wrong conclusions due to loss of information during information processing. Special attention is given to loss of focus on extreme economic outcomes occurring and to distortion of prior knowledge of project base case information. Alternatively, it is proposed to represent uncertain variables by intervals and fuzzy numbers and it is demonstrated that this approach has a number of advantages over the probabilistic approach. By using triangular uncertainty distributions the two approaches are compared and a study of a railway line investment case is presented suggesting that a combination of the two approaches have some potential advantages.
[1]
Roger Pyddoke,et al.
Cost overruns in Swedish transport projects
,
2011
.
[2]
Jonas Eliasson,et al.
Cost overruns and demand shortfalls – Deception or selection?
,
2013
.
[3]
Alan Hájek,et al.
The reference class problem is your problem too
,
2007,
Synthese.
[4]
Bent Flyvbjerg,et al.
From Nobel Prize to Project Management: Getting Risks Right
,
2006,
ArXiv.
[5]
H. Schjaer-Jacobsen,et al.
Representation and calculation of economic uncertainties: Intervals, fuzzy numbers, and probabilities
,
2002
.
[6]
Bent Flyvbjerg,et al.
Procedures for Dealing with Optimism Bias in Transport Planning
,
2004
.
[7]
Dan Lovallo,et al.
Delusion and Deception in Large Infrastructure Projects: Two Models for Explaining and Preventing Executive Disaster
,
2009,
1303.7403.
[8]
H. Schjær-Jacobsen.
Modeling Of Economic Uncertainty
,
2004
.
[9]
Hans Schjaer-Jacobsen.
A new method for evaluating worst- and best-case (WBC) economic consequences of technological development
,
1996
.