A Decentralized and Pull-Based Control Loop for On-Demand Delivery in Eto Construction Supply Chains

Engineer-to-Order (ETO) process chain types with a successive installation on-site are common in plant building and the construction industry. Usually, the core processes Engineering, Fabrication and Installation are disconnected, which creates high levels of Work in Progress (WIP) and long lead-times. Furthermore, up to date information about the construction progress, as prerequisite for an on-demand delivery of ETO-components is always difficult to obtain. Usually, to prevent a lack of material on-site, costly intermediate storages are used, which extend the delivery time. Well-known approaches in research, like the Last Planner System (LPS) or the Location Based Management System (LBMS), increase collaboration on-site and improve the reliability of construction schedules, but have a limited impact on synchronizing the supply chain to the construction progress. The approach presented in the paper describes how off-site and on-site production can be coupled, to reach short construction lead-times without wastefully intermediate storages. A first ITprototype, based on “Industry 4.0” principles, was implemented and tested in an Italian medium-sized ETO construction supplier.

[1]  Erwin Rauch,et al.  Increasing productivity in ETO construction projects through a lean methodology for demand predictability , 2015, 2015 International Conference on Industrial Engineering and Operations Management (IEOM).

[2]  Rafael Sacks,et al.  Assessing research issues in Automated Project Performance Control (APPC) , 2007 .

[3]  Denise Gravitt Location‐Based Management for Construction: Planning, Scheduling and Control , 2011 .

[4]  Rafael Sacks,et al.  Modern Construction: Lean Project Delivery and Integrated Practices , 2013 .

[5]  Patrick Dallasega,et al.  Design of a Framework for Supporting the Execution-Management of Small and Medium sized Projects in the AEC-industry , 2015 .

[6]  Shigeo Shingo,et al.  Non-Stock Production: The Shingo System for Continuous Improvement , 1988 .

[7]  Gregory A. Howell,et al.  SHIELDING PRODUCTION: ESSENTIAL STEP IN PRODUCTION CONTROL , 1998 .

[8]  Patrick Dallasega,et al.  Design of the Building Execution Process in SME Construction Networks , 2013 .

[9]  TU MarioHermann Design Principles for Industrie 4 . 0 Scenarios , 2015 .

[10]  Daisuke Hirotani,et al.  Comparing CONWIP, synchronized CONWIP, and Kanban in complex supply chains , 2005 .

[11]  Glenn Ballard,et al.  Making Prefabrication Lean , 2004 .

[12]  Erwin Rauch,et al.  Sustainability in the supply chain through synchronization of demand and supply in ETO-companies , 2015 .

[13]  Herman Glenn Ballard,et al.  THE LAST PLANNER SYSTEM OF PRODUCTION CONTROL , 2000 .

[14]  Patrick Dallasega A method and IT-framework for On-Demand Delivery in Make-to-Order Construction Supply Chains , 2017 .

[15]  Sustainability in the Automotive Supply Chain , 2012 .