Incorporating aleatory and epistemic uncertainties in the modelling of construction duration

This study aims to develop a model which incorporates the impact of both aleatory and epistemic uncertainties into construction duration predictions, in a manner that is consistent with the nature/quality of information available about various factors which bring about uncertainties.,Data relating to 178 completed Tertiary Education Trust Fund (TETfund) building construction projects were obtained from construction firms via questionnaire survey. Using 90% of the data, the model was developed in the form of a hybrid-based algorithm implemented through a suitable user-friendly graphical user interface (GUI) using MATLAB programming language. Bayesian model averaging, Monte Carlo simulation and fuzzy logic were the statistical methods used for the algorithm development, prior to its GUI implementation in MATLAB. Using the remaining 10% data, the model's predictive accuracy was assessed via the independent samples t-test and the mean absolute percentage error (MAPE).,The developed model's predictions were found not statistically different from those of actual duration estimates in the 10% test data, with a MAPE of just 2%. This suggests that the model's ability to incorporate both aleatory and epistemic uncertainties improves accuracy of duration predictions made using it.,The model was developed using a particular type of building projects (TETfund building construction projects), and so its use is limited to projects with characteristics similar to those used for its development.,The developed model's predictions are expected to serve as a useful basis for consultancy firms and contractor organisations to make more realistic schedules and benchmark measures of construction period, thereby facilitating effective planning and successful execution of construction projects.,The study presented a model which permits combined manipulation of aleatory and epistemic uncertainties, hence ensuring a more realistic incorporation of uncertainty into construction duration predictions.

[1]  Sherif Ali Mohtady Mohamed,et al.  Modelling project investment decisions under uncertainty using possibility theory , 2001 .

[2]  Mohan M. Kumaraswamy,et al.  Modelling and predicting construction durations in Hong Kong public housing , 1999 .

[3]  Wei-Chih Wang,et al.  MODEL FOR EVALUATING NETWORKS UNDER CORRELATED UNCERTAINTY--NETCOR , 2000 .

[4]  Hong Zhang,et al.  Application of Fuzzy Logic to Simulation for Construction Operations , 2003 .

[5]  Keming Yu,et al.  Penalized single-index quantile regression , 2013 .

[6]  Llewellyn Tang,et al.  Simulating Construction Duration for Multistory Buildings with Controlling Activities , 2013 .

[7]  Herbert H. Einstein,et al.  Construction Cost and Duration Uncertainty Model: Application to High-Speed Rail Line Project , 2016 .

[8]  D. R. Ogunsemi,et al.  Time‐cost model for building projects in Nigeria , 2006 .

[9]  Ki-Hyun Um,et al.  Collaboration and opportunism as mediators of the relationship between NPD project uncertainty and NPD project performance , 2018 .

[10]  Simaan M. AbouRizk,et al.  Modeling uncertainty with an integrated simulation system , 2005 .

[11]  Pablo Ballesteros-Pérez,et al.  M-PERT: Manual project-duration estimation technique for teaching scheduling basics , 2017 .

[12]  Ka Chi Lam,et al.  The predictive ability of Bromilow's timecost model , 2001 .

[13]  Hira N. Ahuja,et al.  Simulation Model to Forecast Project Completion Time , 1985 .

[14]  Andrew W Gale,et al.  Conceptualising uncertainty in safety-critical projects: A practitioner perspective , 2015 .

[15]  Brendan A. Wintle,et al.  The Use of Bayesian Model Averaging to Better Represent Uncertainty in Ecological Models , 2003 .

[16]  S. Richardson,et al.  Variable selection and Bayesian model averaging in case‐control studies , 2001, Statistics in medicine.

[17]  Laura Uusitalo,et al.  An overview of methods to evaluate uncertainty of deterministic models in decision support , 2015, Environ. Model. Softw..

[18]  Wenqian Wang,et al.  Uncertainty, opportunistic behavior, and governance in construction projects: The efficacy of contracts , 2018, International Journal of Project Management.

[19]  A. Raftery,et al.  Using Bayesian Model Averaging to Calibrate Forecast Ensembles , 2005 .

[20]  Samuel Labi,et al.  Planning-stage estimation of highway project duration on the basis of anticipated project cost, project type, and contract type , 2011 .

[21]  Mohamed Mohamed Naim,et al.  Identifying and Categorizing the Sources of Uncertainty in Construction Supply Chains , 2013 .

[22]  Mohan M. Kumaraswamy,et al.  Forecasting construction durations for public housing projects: a Hong Kong perspective , 1999 .

[23]  Bilal M. Ayyub,et al.  Fuzzy stochastic risk-based decision analysis with the mobile offshore base as a case study , 2001 .

[24]  Wei Tong Chen,et al.  Approximately predicting the cost and duration of school reconstruction projects in Taiwan , 2006 .

[25]  Nelson J. Trujillo-Barreto,et al.  Bayesian model averaging in EEG/MEG imaging , 2004, NeuroImage.

[26]  Osama Moselhi,et al.  Project-network analysis using fuzzy sets theory , 1996 .

[27]  Dominique Guyonnet,et al.  Comparing Two Methods for Addressing Uncertainty in Risk Assessments , 1999 .

[28]  Adel Francis Simulating Uncertainties in Construction Projects with Chronographical Scheduling Logic , 2017 .

[29]  Peter E.D. Love,et al.  Re-Examining the Association between Quality and Safety Performance in Construction: From Heterogeneous to Homogeneous Datasets , 2017 .

[30]  Mohan M. Kumaraswamy,et al.  A study of the factors affecting construction durations in Hong Kong , 1995 .

[31]  Kenneth H. Reckhow,et al.  Two-Phase Monte Carlo Simulation for Partitioning the Effects of Epistemic and Aleatory Uncertainty in TMDL Modeling , 2019, Journal of Hydrologic Engineering.

[32]  Long Le-Hoai,et al.  Time‐cost relationships of building construction project in Korea , 2009 .

[33]  Mohan M. Kumaraswamy,et al.  Evaluation of factors affecting Time and Cost performance in Hong Kong Building projects , 1999 .

[34]  Guohe Huang,et al.  Hybrid Fuzzy-Stochastic Modeling Approach for Assessing Environmental Risks at Contaminated Groundwater Systems , 2003 .

[35]  Damià Barceló,et al.  How to measure uncertainties in environmental risk assessment , 2008 .

[36]  Albert P.C. Chan Modelling building durations in Hong Kong , 1999 .

[37]  Yolanda Villacampa,et al.  Modeling construction time in Spanish building projects , 2014 .

[38]  Christopher F. Parmeter,et al.  Bayesian Model Averaging in R , 2011 .

[39]  G. Okoboi,et al.  Electricity peak demand in Uganda: insights and foresight , 2016 .