Hole cleaning optimization of horizontal wells with the multi-dimensional ant colony algorithm

Abstract Horizontal wells have been widely used to exploit unconventional oil and gas reservoirs across the world. Insufficient hole cleaning has been recognized as one of the main difficulties in drilling horizontal wells. Drilling incidents caused by insufficient hole cleaning increase unproductive drilling time, induce a great amount of additional drilling costs and may even lead to the loss of the well. Drilling a well while maintaining efficient hole cleaning is a systematic process that requires various parameters to implement hole cleaning and requires cooperative effort rather than separate work. Therefore, optimizing multiple parameters to achieve the best hole cleaning effect is of great importance. However, to the author's knowledge, few research studies in this area have been undertaken. The objective of this study is to develop a new method to optimize multiple hole cleaning parameters by introducing the ant colony algorithm. The flow rate, consistency coefficient in power law model and nozzle flow area, which are three easily-adjusted parameters to control the hole cleaning on drilling site, are selected as the optimization variables. The hydraulic constraints that affect hole cleaning optimization are proposed. The mechanism and procedures of ant colony algorithm optimization are described. The practical usefulness of the developed method is demonstrated with a field example. The effect of the selected parameters on hole cleaning is analyzed, and the hole cleaning result after optimization is compared to the data before optimization. The result of the optimization shows that hole cleaning is greatly improved and all constraints are satisfied after optimization. By analyzing the optimization results, it can be concluded that the ant colony algorithm can be used to optimize the hole cleaning problem for horizontal wells. Artificial intelligence can help optimize the drilling of horizontal wells to reduce the risk of unproductive time and decrease drilling costs. The flow rate, consistency coefficient and nozzle flow area should cooperate with one another to minimize the cutting bed height while satisfying all of the constraints. Increasing the flow rate is the most efficient way to reduce the cutting bed height. Decreasing the consistency coefficient and increasing the nozzle flow area can reduce the total pressure loss and enlarge the capacity for increasing the flow rate. Increasing the pressure-bearing capacity of the system is favorable for improving the hole cleaning of horizontal wells. The cutting bed height can be further reduced and the jet velocity can be further increased when increasing the pressure-bearing capacity of the system.

[1]  J. J. Azar,et al.  Effect of Drillpipe Rotation on Hole Cleaning During Directional-Well Drilling , 1999 .

[2]  Swagatam Das,et al.  Ant colony optimization based enhanced dynamic source routing algorithm for mobile Ad-hoc network , 2015, Inf. Sci..

[3]  José A. Moreno-Pérez,et al.  An ACO hybrid metaheuristic for close-open vehicle routing problems with time windows and fuzzy constraints , 2015, Appl. Soft Comput..

[4]  Hyun Cho,et al.  A Three-Layer Modeling for Cuttings Transport with Coiled Tubing Horizontal Drilling , 2000 .

[5]  Oscar Castillo,et al.  A new approach for dynamic fuzzy logic parameter tuning in Ant Colony Optimization and its application in fuzzy control of a mobile robot , 2015, Appl. Soft Comput..

[6]  S. T. Johansen,et al.  Mechanistic model for cuttings removal from solid bed in inclined channels , 2001 .

[7]  Moacir Godinho Filho,et al.  An ant colony optimization approach for the parallel machine scheduling problem with outsourcing allowed , 2015, J. Intell. Manuf..

[8]  J. J. Azar,et al.  Development of a New Cuttings-Transport Model for High-Angle Wellbores Including Horizontal Wells , 1997 .

[9]  Yulong Zhao,et al.  Performance of fractured horizontal well with stimulated reservoir volume in unconventional gas reservoir , 2014 .

[10]  Ramadan Ahmed,et al.  Transport of Small Cuttings in Extended-Reach Drilling , 2008 .

[11]  Ruihe Wang,et al.  A Three-Segment Hydraulic Model for Annular Cuttings Transport with Foam in Horizontal Drilling , 2008 .

[12]  S. Walker,et al.  The Effects of Particle Size, Fluid Rheology, and Pipe Eccentricity on Cuttings Transport , 2000 .

[13]  Mehdi Behzad,et al.  CFD–DEM approach to investigate the effect of drill pipe rotation on cuttings transport behavior , 2015 .

[14]  Chen Liang Study on hydraulics design of extended reach well , 2008 .

[16]  Hamid Reza Karimi,et al.  An ant colony optimization-based fuzzy predictive control approach for nonlinear processes , 2015, Inf. Sci..

[17]  Qin Zhu,et al.  A quadruple-porosity model for transient production analysis of multiple-fractured horizontal wells in shale gas reservoirs , 2015, Environmental Earth Sciences.

[18]  M. B. Oyeneyin,et al.  Comprehensive Experimental Investigation of Drilled Cuttings Transport in Inclined Wells Including the Effects of Rotation and Eccentricity , 1990 .

[19]  Boyun Guo,et al.  A new method for determining the minimum gas injection rate required for hole cleaning in horizontal gas drilling , 2014 .

[20]  J. J. Azar,et al.  The Effects of Mud Rheology on Annular Hole Cleaning in Directional Wells , 1986 .

[21]  Kamy Sepehrnoori,et al.  Simulation study on the CO2-driven enhanced gas recovery with sequestration versus the re-fracturing treatment of horizontal wells in the U.S. unconventional shale reservoirs , 2014 .

[22]  Stefan Z. Miska,et al.  Selecting drilling fluid properties and flow rates for effective hole cleaning in high-angle and horizontal wells , 2000 .

[23]  Wang Zhiming HYDRAULIC EXTENDED LIMITATION OF EXTENDED-REACH WELL , 2008 .