Critical path identification in planning of winery wastewater plant

Critical Path Method (CPM) is an economic and useful tool to aid managers during preparation and application of projects for scheduling, giving control and coordination, and solving the problems. In this work, CPM is employed for planning Winery Wastewater Treatment Plant. A schedule is calculated by CPM and its network diagram and bar chart of works is prepared with the Primavera Project Planner which is a project management and control software.