Estimating Cost Discrepancies in Highway Contracts: Multistep Econometric Approach

This paper investigates the likelihood of occurrence and quantifies the magnitude and rate of discrepancies in highway project final costs with respect to their contract award amounts. Using data from Indiana, we develop a multistep econometric approach that can be used to estimate the effects of factors associated with the contract bidding process, project type, and the project physical environment on cost discrepancies in highway contracts. Estimation findings indicate that for a given project type and project year, contracts of larger size or longer duration are generally more likely to incur cost overruns. In addition, for contracts that incur cost overruns, the cost overrun rate decreases nonlinearly with increasing contract size up to a certain point after which the cost overrun rate increases with increasing contract size. Our approach allows for the possibility that cost overrun amounts are not linearly related to contract award amounts (contract size), and shows that greater analytical flexibility needs to be incorporated into any investigation of contract cost overruns. Agencies interested in improving their financial forecasts can replicate our proposed methodology using local contract data.

[1]  Trefor P. Williams Bidding ratios to predict highway project costs , 2005 .

[2]  Maynard M. Hufschmidt,et al.  Systematic Errors in Cost Estimates for Public Investment Projects , 1970 .

[3]  S H Daniels,et al.  AUDIT NOTES 'AVOIDABLE' CHANGES , 1998 .

[4]  S. Washington,et al.  Statistical and Econometric Methods for Transportation Data Analysis , 2010 .

[5]  Trefor P. Williams Predicting completed project cost using bidding data , 2002 .

[6]  GERARD DE JONG,et al.  National and International Freight Transport Models: An Overview and Ideas for Future Development , 2004 .

[7]  Francis T. Hartman,et al.  Construction Claims and Disputes: Causes and Cost/Time Overruns , 1994 .

[8]  James Odeck,et al.  Cost overruns in road construction--what are their sizes and determinants? , 2004 .

[9]  Charles T. Jahren,et al.  Predictors of Cost‐Overrun Rates , 1990 .

[10]  Tarek Hegazy,et al.  Predicting cost deviation in reconstruction projects: Artificial neural networks versus regression , 2003 .

[11]  B. Akinci,et al.  FACTORS AFFECTING CONTRACTORS' RISK OF COST OVERBURDEN , 1998 .

[12]  J. P. Connolly Discussion of “Bid-Spread” by Martin Skitmore, Derek Drew, and Stephen Ngai , 2002 .

[13]  Søren L. Buhl,et al.  What Causes Cost Overrun in Transport Infrastructure Projects? , 2004, 1304.4476.

[14]  Aminah Robinson Fayek,et al.  Use of fuzzy logic for predicting design cost overruns on building projects , 2002 .

[15]  Søren L. Buhl,et al.  How common and how large are cost overruns in transport infrastructure projects? , 2003 .

[16]  Samuel Labi,et al.  An Analysis of Cost Overruns and Time Delays of INDOT Projects , 2004 .

[17]  Edem O. P. Akpan,et al.  METHODOLOGY FOR DETERMINING PRICE VARIATION IN PROJECT EXECUTION , 2001 .

[18]  Samuel Labi,et al.  Transportation Decision Making: Principles of Project Evaluation and Programming , 2007 .

[19]  Henry J Rowland The Causes and Effects of Change Orders on the Construction Process. , 1981 .

[20]  Keith R. Molenaar,et al.  Guidance for Cost Estimation and Management for Highway Projects During Planning, Programming, and Preconstruction , 2006 .

[21]  Andrew S. Chang Reasons for cost and schedule increase for engineering design projects , 2002 .

[22]  D. McFadden Econometric Models of Probabilistic Choice , 1981 .