The Analysis on Energy Saving Reconstruction of a Grade III-A General Hospital in Wuhan
暂无分享,去创建一个
Take one of Grade III-A general hospitals in Wuhan as the research object with auditing the hospital's energy consuming system. It can be proved that the energy consumption per unit area is 27kgce/m2 , analysis of typical of the hospital exterior envelope, lighting systems, central heating and air conditioning system for hospital energy, gave priority to recycle the boiler flue gas heat and condensation water, natural light using, exterior windows transforming and installation of the sub-metering systems for energy saving renovation. The comprehensive transformation energy-saving rate is 31.71%. Energy saving quantity is 318.01tce. A total investment is 4.3948 million yuan. The payback period is 2.5 years.