Abstract An activity-on-arc network project of PERT type with random activity durations is considered. The progress of the project cannot be inspected and measured continuously, but only at preset inspection points. An on-line control model has to determine both inspection points and control actions to be introduced at those points to alter the progress of the project in the desired direction. On-line control is carried out to minimize the number of inspection points needed to meet the target, subject to the chance constraint. In the recently developed control models, determining the next inspection point is carried out via extensive simulation with a constant time step. This determination is based on sequential statistical analysis at each intermediate point to maximize the time span between two adjacent control points. The main shortcoming of the control algorithm is its long computational time due to the need to make numerous decisions. In this paper we present a newly developed heuristic control algorithm in which the timing of inspection points does not comprise intermediate decision making. Given a routine inspection point t i , the adjacent point t i +1 is determined so that even if the project develops most unfavorably in the interval [ t i , t i +1 ], introducing proper control action at moment t i +1 enables the project to meet its target on time, subject to the chance constraint. The newly developed control algorithm is essentially more efficient than the step-by-step control procedures. The computational time is reduced by a factor of 25–30 while the algorithm provides better solutions than would be attained by using on-line sequential statistical analysis. Extensive experimentation has been undertaken to illustrate the comparative efficiency of the presented algorithm.
[1]
Richard J. Schonberger,et al.
Why Projects Are “Always” Late: A Rationale Based on Manual Simulation of a PERT/CPM Network
,
1981
.
[2]
Hossein Arsham,et al.
Managing project activity-duration uncertainties
,
1993
.
[3]
Aw Pearson.
Planning and control in research and development
,
1990
.
[4]
רבקה פריאור.
מקבלי דמי פגיעה, 1988
,
1990
.
[5]
D. Golenko-Ginzburg.
Controlled alternative activity networks for project management
,
1988
.
[6]
A Gonik,et al.
On-line control model for network construction projects
,
1997
.
[7]
Dmitri Golenko-Ginzburg,et al.
A Two-Level Production Control Model with Target Amount Rescheduling
,
1990
.
[8]
אסתר טולידנו.
מקבלי דמי אבטלה בשנת 1989
,
1990
.
[9]
Klaus Neumann,et al.
Stochastic Project Networks
,
1990
.
[10]
Gary I. Green,et al.
A Framework for Evaluating Network Planning and Control Techniques
,
1981
.
[11]
D. Golenko-Ginzburg,et al.
Production control with variable speeds and inspection points
,
1989
.
[12]
Dimitri Golenko-Ginzburg.
A two-level decision-making model for controlling stochastic projects
,
1993
.
[13]
Dimitri Golenko-Ginzburg,et al.
On-line Control Model for Cost-simulation Network Projects
,
1996
.