Periodic Inspections of Cleveland Harbor East Breakwater, Ohio, and Burns Harbor North Breakwater, Indiana

Abstract : Monitoring Completed Navigation Projects (MCNP) Program evaluates the structural and functional performance of existing navigation structures. Under Periodic Inspections, aerial photography, ground-truth surveys, walking inspections, photogrammetry, and lidar elevation data are used to periodically assess the structural conditions of selected structures. A database of these structures is being compiled for asset management and other purposes. Cleveland Harbor East Breakwater, OH, has sustained extensive damage since its construction in 1915. The Breakwater has had an extensive repair history, including a major rehabilitation in 1979 80 involving the placement of 2-ton dolosse on the lakeward slope and crest of the easterly 4,400 feet (ft). Some failed and were replaced with 4-ton dolosse. Other repairs took place in 1986, 1989, 1991, and 2001 on the nondolos sections. Burns Harbor North Breakwater, IN, is a 4,640 ft rubble-mound structure constructed in 1969. The Breakwater has required extensive maintenance including the addition of 290 kilotons of stone through 1989. A submerged reef was constructed between 1995 and 1998, 75 ft lakeward of the Breakwater, to reduce wave energy reaching the structure.

[1]  Robert R. Bottin,et al.  Inspections of Previously Monitored Coastal Structures. , 1999 .

[2]  Robert R. Bottin,et al.  Periodic Inspection of Cleveland Harbor East Breakwater, Ohio. Report 1, Base Conditions. , 1995 .

[3]  Grady Tuell,et al.  Overview of the coastal zone mapping and imaging lidar (CZMIL): a new multisensor airborne mapping system for the U.S. Army Corps of Engineers , 2010, Defense + Commercial Sensing.

[4]  Robert D. Carver,et al.  Reef Breakwater Wave-Attenuation and Stability Tests, Burns Waterway Harbor, Indiana. , 1995 .

[5]  Robert R Bottin Case Histories of Corps Breakwater and Jetty Structures. Report 3. North Central Division , 1988 .

[6]  Robert R. Bottin,et al.  Inspections of Previously Monitored Rubble-Mound Coastal Structures , 2004 .

[7]  Molly Reif,et al.  A review of U.S. Army Corps of Engineers airborne coastal mapping in the Great Lakes , 2013 .

[8]  Robert R Bottin,et al.  Monitoring of East Breakwater Rehabilitation at Cleveland Harbor, Ohio , 1993 .

[9]  Dennis G. Markle,et al.  Wave stability tests of dolos and stone rehabilitation designs for the east breakwater, Cleveland Harbor, Ohio : experimental model investigation , 1985 .

[10]  Jennifer L Irish An Introduction to Coastal Zone Mapping With Airborne Lidar: The Shoals System , 2000 .

[11]  Jeffrey A. Melby,et al.  Concrete Armor Unit Performance in Light of Recent Research Results , 1995 .

[12]  David D. McGehee,et al.  Burns Harbor, Indiana, Monitoring Study, Volume 1: Overview of Approach and Results , 1997 .

[13]  Robert R. Bottin,et al.  Periodic Inspection of Burns Harbor North Breakwater, Indiana. Report 1, Base Conditions. , 1996 .

[14]  L. Hales,et al.  Guidance and lessons learned from monitoring completed navigation projects , 2004 .