Optimal Spatial Arrangement of Shipbuilding Blocks in the Pre-erection Area of Shipyard

The major problem arises at shipyard is because of scarcity of space for arranging the building blocks of ship under construction. A standardized erection sequence diagram is generally available to provide the prioritized erection sequence and it serves as the frame work. In order to make a timely erection of the blocks a post plan has to be developed so that the blocks lie in the nearest possible vicinity of the material handling devices while keeping the priority of erection and the blocks are arranged in the pre-erection area. This kind of readiness of blocks leads to a very complex problem of space. This arises due to the least available space leading to an urgent need for intelligent spatial schedule without compromising the rate of production. There exists two critical problems ahead namely, the spatial occupation layout of pre-erection area and the evacuating pattern in the spatial vicinity. The block shape is assumed be rectangular. The related input data's are the dates of erection (earliest as well as the latest), geometrical parameters of block available on pre-erection area, slack time and the like. World over industrial engineers and decision makers are brainstorming hard to find an ideal solution for their unique problems. Every scheduling and decisional problems end up in complicated iterative loop system.