Scheduling and control of linear projects
暂无分享,去创建一个
A two-state-variable, N-stage dynamic programming approach to scheduling and control of linear projects is presented. This approach accounts for practical considerations related to work continuity, interruptions, and lags between successive activities. In the dynamic programming formulation, stages represent project activities and state variables represent possible activity resources and interruptions at each location. The objective of the dynamic programming solution is to provide for the selection of resources, interruptions, and lags for production activities that lead to the minimum project total cost. In addition, the presented system produces a graphical presentation of the optimum project schedule and updates the original schedule based on update information input by the user. The updated schedule determines the new completion date, and forecasts the project new total cost based on the current project performance. A small linear project is provided as a numerical illustration of the system. Key wor...