Approximately predicting the cost and duration of school reconstruction projects in Taiwan

Regression and neural network models have been developed to predict the cost and duration of projects for the reconstruction of schools which must be quickly rebuilt. Data for the school reconstruction projects in central Taiwan, which received the most serious damage from the Chi‐Chi Earthquake, were collected and analysed. The analytical results demonstrate that the floor area provides a good basis for estimating the cost and duration of school reconstruction projects, and suggest that the neural network model with back‐propagation learning technique is a feasible approach that yields better prediction results than the regression model for school reconstruction projects.

[1]  Geoffrey E. Hinton,et al.  Learning internal representations by error propagation , 1986 .

[2]  Derek H.T. Walker,et al.  An investigation into construction time performance , 1995 .

[3]  Geoffrey E. Hinton,et al.  A general framework for parallel distributed processing , 1986 .

[4]  Mohan M. Kumaraswamy,et al.  Determinants of construction duration , 1995 .

[5]  David Lowe,et al.  Data modelling and the application of a neural network approach to the prediction of total construction costs , 2002 .

[6]  Trefor P. Williams Predicting completed project cost using bidding data , 2002 .

[7]  Wei-Chih Wang,et al.  Contractor selection by the most advantageous tendering approach in Taiwan , 2003 .

[8]  Mohan M. Kumaraswamy,et al.  A study of the factors affecting construction durations in Hong Kong , 1995 .

[9]  Michael D Dalzell,et al.  Everything old is new again. , 2007, Biotechnology healthcare.

[10]  Albert P.C. Chan Modelling building durations in Hong Kong , 1999 .

[11]  Goh Bee-Hua,et al.  An evaluation of the accuracy of the multiple regression approach in forecasting sectoral construction demand in Singapore , 1999 .

[12]  George J. Tamaro,et al.  Exchange Place Station Subsurface Reconstruction and Improvements , 1992 .

[13]  Mohan M. Kumaraswamy,et al.  Modelling and predicting construction durations in Hong Kong public housing , 1999 .

[14]  Albert P.C. Chan Time–cost relationship of public sector projects in Malaysia , 2001 .

[15]  Dov Kaminetzky,et al.  Success or Failure: A Tale of Two Projects , 1996 .

[16]  Tarek Hegazy,et al.  Predicting cost deviation in reconstruction projects: Artificial neural networks versus regression , 2003 .

[17]  Vernon Ireland,et al.  The role of managerial actions in the cost, time and quality performance of high-rise commercial building projects , 1985 .