Construction workspace management within an Industry Foundation Class-Compliant 4D tool

Workspaces on construction sites represent a key resource due to their limited availability and impact on work progress and safety. The augmentation of traditional scheduling techniques (e.g., CPM, PERT) with both visualisation and new capabilities to address emerging challenges such as workspace management attracted a significant interest in recent years. Studies in this area addressed individual processes of workspace management such as workspace modelling and allocation and spatial conflict detection and resolution and were often performed in non-4D environments. This research presents the results from the development and evaluation of a methodology and an Industry Foundation Class (IFC) compliant 4D tool for workspace management. The methodology and the tool provide a holistic solution to the approach of workspace management through the allocation of workspaces to site activities, the detection of congestion, spatial and temporal conflicts and their resolution within a 4D environment in an interactive real-time manner, aided with analytic data from a centralised database.

[1]  David Heesom,et al.  Model-Based Groupware Solution for Distributed Real-Time Collaborative 4D Planning through Teamwork , 2012, J. Comput. Civ. Eng..

[2]  B. T. Talhouni,et al.  Effects of Accelerated Working, Delays and Distruption on Labour Productivity , 1996 .

[3]  Christer Ericson,et al.  Real-Time Collision Detection , 2004 .

[4]  Nashwan Dawood,et al.  Construction Workspace Planning: Assignment and Analysis Utilizing 4D Visualization Technologies , 2006, Comput. Aided Civ. Infrastructure Eng..

[5]  Wei Wu Key Issues in Workforce Planning and Adaptation Strategies for BIM Implementation in Construction Industry , 2014 .

[6]  Gilles Halin,et al.  Designing adapted visualization for collaborative 4D applications , 2013 .

[7]  Nashwan Dawood,et al.  Multi-constraint information management and visualisation for collaborative planning and control in construction , 2003, J. Inf. Technol. Constr..

[8]  Gunnar Lucko,et al.  Spatially-Constrained Scheduling with Multi-Directional Singularity Functions , 2014 .

[9]  Shih-Chung Kang,et al.  Collision detection strategies for virtual construction simulation , 2009 .

[10]  Marc M. Sebrechts,et al.  HANDBOOK OF VIRTUAL ENVIRONMENTS , 2014 .

[11]  Meng-Han Tsai,et al.  Selection and evaluation of color scheme for 4D construction models , 2013, J. Inf. Technol. Constr..

[12]  Nashwan Dawood,et al.  Development of workspace conflict visualization system using 4D object of work schedule , 2014, Adv. Eng. Informatics.

[13]  Graham Winch,et al.  Critical Space Analysis , 2006 .

[14]  Sy-Jye Guo,et al.  Identification and Resolution of Work Space Conflicts in Building Construction , 2002 .

[15]  Jonathan Jingshen Shi,et al.  Object-oriented resource-based planning method (ORPM) for construction , 2000 .

[16]  Timo Hartmann,et al.  Aligning building information model tools and construction management methods , 2012 .

[17]  Kwok-wing Chau,et al.  Four-dimensional visualization of construction scheduling and site utilization , 2004 .

[18]  Xing Su,et al.  Life Cycle Approach to Construction Workspace Modeling and Planning , 2014 .

[19]  David Greenwood,et al.  An efficient method for scheduling construction projects with resource constraints , 2001 .

[20]  Nashwan Dawood,et al.  The virtual construction site (VIRCON) tools: An industrial evaluation , 2005, J. Inf. Technol. Constr..

[21]  Bonsang Koo,et al.  Feasibility study of 4D CAD in commercial construction , 2002 .

[22]  Vacharapoom Benjaoran,et al.  Enhancing visualization of 4D CAD model compared to conventional methods , 2009 .

[23]  H R Thomas,et al.  LOSS OF CONSTRUCTION LABOR PRODUCTIVITY DUE TO INEFFICIENCIES AND DISRUPTIONS: THE WEIGHT OF EXPERT OPINION , 1990 .

[24]  Yumei Xiong,et al.  An Improved Bounding Box Algorithm to Collision Detection for Virtual Environment , 2011 .

[25]  M. Scriven The methodology of evaluation , 1966 .

[26]  Martin Fischer,et al.  Automated Generation of Work Spaces Required by Construction Activities , 2002 .

[27]  Nashwan Dawood,et al.  Development of 4D based performance indicators in construction industry , 2009 .

[28]  Hyeon-Seung Kim,et al.  Development of a schedule-workspace interference management system simultaneously considering the overlap level of parallel schedules and workspaces , 2014 .

[29]  Yvan J. Beliveau,et al.  Modeling Work Space to Schedule Repetitive Floors in Multistory Buildings , 1994 .

[30]  M. Goetschalckx Supply Chain Models , 2011 .

[31]  Zhen-Zhong Hu,et al.  BIM- and 4D-based integrated solution of analysis and management for conflicts and structural safety problems during construction: 1. Principles and methodologies , 2011 .

[32]  David Heesom,et al.  Trends of 4D CAD applications for construction planning , 2004 .

[33]  Rafael Sacks,et al.  Spatial and Temporal Exposure to Safety Hazards in Construction , 2009 .

[34]  Burcu Akinci,et al.  Automated generation of workspace requirements of mobile crane operations to support conflict detection , 2007 .

[35]  Oleg A. Tarlapan,et al.  Effective project scheduling under workspace congestion and workflow disturbance factors , 2013 .

[36]  Tarek Hegazy,et al.  DYNAMIC LAYOUT OF CONSTRUCTION TEMPORARY FACILITIES CONSIDERING SAFETY , 2004 .

[37]  Nashwan Dawood,et al.  A framework for the integration and coordination of the construction supply chain , 2013, Int. J. Bus. Perform. Supply Chain Model..

[38]  Sang-Youb Lee,et al.  Optimization of floor-level construction material layout using Genetic Algorithms , 2007 .