Tracking stator bar condition by on-line partial discharge measurements
暂无分享,去创建一个
A total of 24 new stator bar windings in hydrogenerators were equipped with 80 pF permanent couplers for on-line partial discharge measurements beginning in 1979. This paper summarizes some of the changes in the PD characteristics that have occurred over the years and correlates significant changes with the condition of the windings.
[1] W McDermid,et al. The ramp test - its origins, development and application , 2010, IEEE Transactions on Dielectrics and Electrical Insulation.
[2] W. McDermid,et al. Experience with directional couplers for partial discharge measurements on rotating machines in operation , 1999 .