An Investigation into Factors Causing Delays in Road Construction Projects in Kenya

The majority of road construction projects in Kenya do not get completed within the initially set targets of time. Project delays frustrate the process of development, have an immeasurable cost implication to the society, and also lead to loss of reputation of the parties involved in the projects’ execution. The purpose of this study was to investigate the factors causing delays in road construction projects in Kenya. Project delays are a common problem internationally in the construction industry in modern times. Investigating the reasons for delay has become an important contribution to improved construction industry performance. Over seventy percent of projects initiated in Kenya are likely to escalate in time with a magnitude of over fifty percent. The study used purposive sampling technique and survey design. Data was collected using questionnaires which were distributed to consultants and contractors. The data was analyzed using the Relative Importance Index and Spearman’s rank correlation. The top five causes of project delays were observed to be payment by client, slow decision making and bureaucracy in client organization, inadequate planning and scheduling, and rain. It is recommended that clients should improve their financial management systems so that they are able to pay contractors in a timely manner. Bureaucracy and red tape should be reduced in client organizations in order to speed up the slow decision making process. Efficient management of the construction process will also lead to a reduction in incidences of claims. Contractors should prepare adequate plans and schedules which can also be used to minimize the effects of rain.

[1]  Paul. Olomolaiye,et al.  Attributes of UK construction clients influencing project consultants' performance , 1994 .

[2]  Hesham A. Bassioni,et al.  Causes of Delay in Building Construction Projects in Egypt , 2008 .

[3]  C. R. Kothari,et al.  Research Methodology: Methods and Techniques , 2009 .

[4]  Alfred Atsango B. A Talukhaba Time and cost performance of Construction Project , 1988 .

[5]  Ibrahim Mahamid Frequency of time overrun causes in road construction in Palestine: Contractors' View , 2013 .

[6]  Aftab Hameed Memon CONTRACTOR PERSPECTIVE ON TIME OVERRUN FACTORS IN MALAYSIAN CONSTRUCTION PROJECTS , 2014 .

[7]  N. Mansfield,et al.  Causes of delay and cost overruns in Nigerian construction projects , 1994 .

[8]  Ernawati,et al.  The significant factors causing delay of building construction projects in Malaysia , 2007 .

[9]  Wynand Jacobus Van der Merwe Steyn,et al.  Causes of delay in road construction projects in Malawi , 2013 .

[10]  Thomas E. Uher,et al.  Cost estimating practices in Australian construction , 1996 .

[11]  Alfred A Talukhaba An investigation into factors causing construction project delays in Kenya case study of high rise building projects in Nairobi , 1999 .

[12]  Lynn Crawford,et al.  Causes of delay and cost overruns in construction of groundwater projects in a developing countries; Ghana as a case study , 2003 .

[13]  V. Krishnamoorthy,et al.  Study on the Quantification of Delay Factors in Construction Industry , 2014 .

[14]  D. A. R. Dolage,et al.  Causes of time overrun in construction phase of building projects : a case study on Department of Engineering Services of Sabaragamuwa Provincial Council , 2013 .

[15]  Adwoa Difie Ampadu-Asiamah,et al.  Management of Government Funded Construction Projects in Ghana: Stakeholders’ Perspective of Causes of Delays in Construction of Public Buildings. , 2013 .

[16]  Ayman Abu Hammad,et al.  Delays in construction projects: The case of Jordan , 2008 .

[17]  Sadi Assaf,et al.  Causes of delay in large construction projects , 2006 .

[18]  Al Tabtabai,et al.  Causes For Delays In Construction Projects In Kuwait , 2002 .

[19]  N David Kagiri Time and cost overruns in power projects in Kenya: A case study of Kenya electricity generating Company limited , 2005 .

[20]  Raymond N. Nkado Construction time information system for the building industry , 1992 .

[21]  Ghaleb J. Sweis Factors Affecting Time Overruns in Public Construction Projects: The Case of Jordan , 2013 .

[22]  Michiel Bekker,et al.  Causes of construction cost and time overruns: The 2010 FIFA World Cup stadia in South Africa , 2011 .

[23]  Geraldine J. Kikwasi,et al.  Causes and Effects of Delays and Disruptions in Construction Projects in Tanzania , 2013 .

[24]  Borvorn Israngkura Na Ayudhya Evaluation of Common Delay Causes of Construction Projects in Singapore , 2011 .

[25]  Sameh M. El-Sayegh,et al.  Significant factors causing delay in the UAE construction industry , 2006 .

[26]  Peter T Kivaa Developing a model for estimating construction period: a survey of building projects in Nairobi , 2001 .

[27]  M. Ishaq Nadiri,et al.  Contribution of highway capital to output and productivity growth in the US economy and industries , 1998 .

[28]  S. Ogunlana,et al.  Construction delays in a fast-growing economy: Comparing Thailand with other economies , 1996 .

[29]  S. Fan,et al.  Road Development, Economic Growth, and Poverty Reduction in China: , 2005 .

[30]  D Walker Investigation into factors that determine building construction time performance , 1994 .

[31]  Ismail Abdul Rahman,et al.  Time and Cost Performance in Construction Projects in Southern and Central Regions of Peninsular Malaysia , 2012 .

[32]  Long Le-Hoai,et al.  Delay and cost overruns in Vietnam large construction projects: A comparison with other selected countries , 2008 .

[33]  Andi Andi,et al.  Owner and Contractor Perceptions Toward Factors Causing Delays in Structural and Finishing Works , 2010 .

[34]  Mohamed Tkiouat,et al.  Identification of the Causes of Deadline Slippage in Construction Projects: State of the Art and Application , 2012 .

[35]  Olajide Timothy Ibironke,et al.  Analysis of Non-Excusable Delay Factors Influencing Contractors' Performance in Lagos State, Nigeria , 2013 .

[36]  Murali Sambasivan,et al.  Causes and effects of delays in Malaysian construction industry , 2007 .

[37]  Frank Fugar,et al.  Delays in Building Construction Projects in Ghana , 2010 .

[38]  V. Vimonsatit,et al.  A study of the factors affecting construction time in Western Australia , 2012 .

[39]  Christopher M Mbatha Building Contract Performance: A Case Study Of Government Projects In Kenya , 1986 .

[40]  Sadi Assaf,et al.  Causes of Delay in Large Building Construction Projects , 1995 .

[41]  Jing Zhou,et al.  Importance and ranking evaluation of delay factors for development construction projects in Benin , 2013 .

[42]  D. B. Desai,et al.  CAUSES OF DELAY IN INDIAN TRANSPORTATION INFRASTRUCTURE PROJECTS , 2013 .

[43]  Henry Mwanaki Alinaitwe,et al.  Investigation into the Causes of Delays and Cost Overruns in Uganda's Public Sector Construction Projects , 2013 .

[44]  Amusan Lekan,et al.  CAUSES AND EFFECT OF DELAY ON PROJECT CONSTRUCTION DELIVERY TIME , 2014 .

[45]  Ismail Abdul Rahman,et al.  Causes of Delay in MARA Management Procurement Construction Projects , 2010 .