An Investigation Into the Delays in Road Projects in Bahrain

This research investigated the delays in road projects in Bahrain. It studied frequency and severity of delay’s causes, as well as frequency of delay’s effects in such projects. Forty seven causes were identified and classified by responsibility into six groups. A field survey was conducted through a questionnaire including 36 contractors, 24 consultants and 84 engineers working at Ministry of Works (MOW). The researcher concluded that there are many causes of delay related to contractors such as the improper planning and scheduling. One of the major causes related to the owner, i.e. MOW is delay in decision making. The main problems related to consultants are due to lack of experience. Moreover, cost and time overruns were two of the most frequent effects of delay.