Causes of Delay in Construction Projects in the Oil and Gas Industry in the Gulf Cooperation Council Countries: A Case Study

Several studies investigating the causes of delay in projects in the construction industry have been conducted worldwide. This study investigates the causes of delay in construction projects in oil and gas processing facilities in Oman and serves as a case study for the Gulf Cooperation Council (GCC) countries. Using a questionnaire, data were collected from 59 project managers employed in different organizations in the oil and gas industry in Oman. The survey results showed a high degree of agreement among the perceptions of project stakeholders, clients, contractors, and consultants on the causes of project delay, and there is no evidence to suggest that the causes of project delay differ significantly according to organization size or organizational ownership. Moreover, seven factors were identified as the major causes of project delay. Although six of these identified elements are general factors that can account for delay in any project in any industry, one of them—poor interaction with vendors in the engineering and procurement stages—is found to be unique to construction projects in the oil and gas industry. The findings of this study could be of value to organizations that are planning to conduct construction projects for oil and gas processing facilities in Oman and other nations with similar environments, such as the GCC countries.

[1]  G. O. Jagboro,et al.  The effects of construction delays on project delivery in Nigerian construction industry , 2002 .

[2]  P. Dey,et al.  Risk management in oil and gas construction projects in Vietnam , 2007, Risk Management in Engineering and Construction.

[3]  Paul Dreyfus,et al.  Are small manufacturers failing the quality test? , 2000, Ind. Manag. Data Syst..

[4]  Mohammed Al-Khalil,et al.  Delay in public utility projects in Saudi Arabia , 1999 .

[5]  N. Mansfield,et al.  Causes of delay and cost overruns in Nigerian construction projects , 1994 .

[6]  Amiruddin Ismail,et al.  Significant factors causing and effects of delay in Iranian construction projects , 2011 .

[7]  Chabota Kaliba,et al.  Cost escalation and schedule delays in road construction projects in Zambia , 2009 .

[8]  Cengiz Haksever,et al.  Total Quality Management in the small business environment , 1996 .

[9]  Sameh M. El-Sayegh,et al.  Significant factors causing delay in the UAE construction industry , 2006 .

[10]  Davide Geneletti,et al.  UK and Italian EIA systems: A comparative study on management practice and performance in the construction industry , 2012 .

[11]  Mohammad Hossein Fallahnejad,et al.  Delay causes in Iran gas pipeline projects , 2013 .

[12]  Stephen Olejnik,et al.  Planning Educational Research: Determining the Necessary Sample Size. , 1984 .

[13]  N. Kartam,et al.  Delays and cost increases in the construction of private residential projects in Kuwait , 2005 .

[14]  M. Kumaraswamy,et al.  Assembling integrated project teams for joint risk management , 2005 .

[15]  M. Haseeb,et al.  PROBLEMS OF PROJECTS AND EFFECTS OF DELAYS IN THE CONSTRUCTION INDUSTRY OF PAKISTAN , 2012, Australian Journal of Business and Management Research.

[16]  Mohan M. Kumaraswamy,et al.  Delays and cost overruns in the construction projects in the Gaza Strip , 2009 .

[17]  Joseph R. Proctor Golden Rule of Contractor-Subcontractor Relations , 1996 .

[18]  George Jergeas,et al.  Analysis of the Front-End Loading of Alberta Mega Oil Sands Projects , 2008 .

[19]  Theodore J. Kratt Poor Communication of Schedule and Cost Control Data Between Construction Site Management and Field Supervision Improved by the Weekly Cost and Schedule Meeting for Direct Labor Supervisors , 1989 .

[20]  T. Mezher,et al.  Causes of delays in the construction industry in Lebanon , 1998 .

[21]  Steve Easterbrook,et al.  Communication Problems in Requirements Engineering: A Field Study , 1996 .

[22]  Stephen O. Ogunlana,et al.  Problems causing delays in major construction projects in Thailand , 2008 .

[23]  Kevin R. McDonald Russian raw materials: Converting threat into opportunity , 1994 .

[24]  Long Le-Hoai,et al.  Delay and cost overruns in Vietnam large construction projects: A comparison with other selected countries , 2008 .

[25]  Ernawati,et al.  The significant factors causing delay of building construction projects in Malaysia , 2007 .

[26]  Tommy Y. Lo,et al.  Construction Delays in Hong Kong Civil Engineering Projects , 2006 .

[27]  Sanjay L. Ahire,et al.  Quality management in large vs small firms: An emperical investigation , 1996 .

[28]  S. Ogunlana,et al.  Construction delays in a fast-growing economy: Comparing Thailand with other economies , 1996 .

[29]  Faisal Manzoor Arain,et al.  Major causes of problems between contractors and subcontractors in the Gaza Strip , 2012 .

[30]  J. A. Heimer,et al.  Logistics Problems in Developing Remote Oil Fields - A Case History From Prudhoe Bay , 1978 .

[31]  Stephen O. Ogunlana,et al.  Quantifying schedule risk in construction projects using Bayesian belief networks , 2009 .

[32]  Prasanta Kumar Dey,et al.  Project risk management using multiple criteria decision-making technique and decision tree analysis: a case study of Indian oil refinery , 2012 .

[33]  Patrick X.W. Zou,et al.  Understanding the key risks in construction projects in China , 2007 .

[34]  Sadi Assaf,et al.  Causes of delay in large construction projects , 2006 .

[35]  Chimay J. Anumba,et al.  Potential for improving site management practices through knowledge management , 2006 .

[36]  Ayman H. Al-Momani,et al.  Construction delay: a quantitative analysis , 2000 .

[37]  Murali Sambasivan,et al.  Causes and effects of delays in Malaysian construction industry , 2007 .

[38]  George Jergeas,et al.  Why Cost and Schedule Overruns on Mega Oil Sands Projects , 2010 .

[39]  Ayman Abu Hammad,et al.  Delays in construction projects: The case of Jordan , 2008 .

[40]  Mohan M. Kumaraswamy,et al.  A comparative study of causes of time overruns in Hong Kong construction projects , 1997 .

[41]  Hesham A. Bassioni,et al.  Causes of Delay in Building Construction Projects in Egypt , 2008 .

[42]  Jianxin Hu,et al.  Impacts of overseas management structures on project buyout management : case studies of Chinese international contractors , 2008 .

[43]  A. M. Odeh,et al.  Causes of construction delay: traditional contracts , 2002 .

[44]  Seung Heon Han,et al.  Analyzing Schedule Delay of Mega Project: Lessons Learned From Korea Train Express , 2009, IEEE Transactions on Engineering Management.

[45]  Lynn Crawford,et al.  Causes of delay and cost overruns in construction of groundwater projects in a developing countries; Ghana as a case study , 2003 .

[46]  Gary David Holt,et al.  Factors influencing construction time and cost overruns on high-rise projects in Indonesia , 1997 .

[47]  Ravichandran Manoharan,et al.  Subcontractor selection method using analytic hierarchy process , 2005 .