제철소 원료 하역 일정계획 시스템

At an integrated steel mill, raw materials such as coal and iron ore are discharged by ships through multiple unloaders. The discharged raw material is then transported to storage yards through multiple routes established simultaneously on a fairly complicated belt conveyer network. Formulating an efficient unloading schedule is a quite cumbersome task due to the insufficient number of berths and unloaders as well as the potential conflict among routes being used simultaneously. In this paper, we propose a solution approach to the scheduling problem and describe the prototype system that we built as an implementation of our approach.