풍력발전단지가 연계된 전력계통에서 상정고장을 고려한 발전력 재조정에 관한 연구

This paper studies on effective rescheduling of generation when the single line contingency has occurred in power system with wind farm. The suggested method is formulated to minimize the rescheduling cost of conventional and wind generators to alleviate congestion. The generator rescheduling method has been used with incorporation of wind farms in the power system. Since all sensitivity is different about congestion line, Line Outage Distribution Factor(LODF) and Generator Sensitivity Factor(GSF) is used to alleviate congestion. The formulation have been proccessed using linear programming(LP) optimization techniques to alleviate transmission congestion. The effectiveness of the proposed rescheduling of generation method has been analyzed on revised IEEE 30-bus systems.