Production scheduling with uncertain demand and no stockkeeping
暂无分享,去创建一个
We consider a production process, in which one part forms the bottle-neck. For this situation, in which there is great uncertainty about future demands and no products are kept in stock, we describe a method for production scheduling and present some results. The most important feature of the method is that some orders are scheduled on arriving and other orders, with a greater agreed due-data unreliability, are scheduled at a later moment.