Out-of-step protection for hydro-generators of power plant at Three Gorges left bank

Out-of-step protection equipped with VGS hydro-generators of Three Gorges power plant, which came to commission in 2003,is introduced.Thereinto,principle,logic and parameters setting of out-of-step protection are detailed. The impedance settings and maximum frequency power swing in parameters setting are discussed.