Daily Work Reports-Based Production Rate Estimation for Highway Projects

AbstractProduction rate estimation of major construction activities in a project play an important role in the planning of resources, tracking project progress, and determining contract time of construction projects as these activities typically fall in the critical path of the project schedule. This paper discusses the possiblity that readily available data from highway agencies such as Daily Work Reports (DWRs), soil data, average traffic information, and weather information can be successfully used to identify and assess significant factors that must be considered in estimating the production rates of major highway activities and to develop production rate estimation models. Common production rate estimation methods such as expert opinion, engineering judgment, and production rate charts may lead to erratic production rate estimation by comparing the production rates calculated and estimated through different methods. Actual project data–based production rate estimation might be the most reliable metho...

[1]  W F McFarland,et al.  CONSTRUCTION CONTRACT TIME DETERMINATION. FINAL REPORT , 1992 .

[2]  Elaine N. Aron,et al.  Statistics for the Behavioral and Social Sciences: A Brief Course , 1996 .

[3]  James T. O'Connor,et al.  Crew production rates for contract time estimation : Beam erection, deck, and rail of highway bridges , 2006 .

[4]  Giovanni C. Migliaccio,et al.  Construction Equipment Management , 2019 .

[5]  Eul-Bum Lee,et al.  Productivity Aspects of Urban Freeway Rehabilitation With Accelerated Construction , 2007 .

[6]  Simaan M. AbouRizk,et al.  Estimating Labor Production Rates for Industrial Construction Activities , 2001 .

[7]  Nang-Fei Pan,et al.  Assessment of productivity and duration of highway construction activities subject to impact of rain , 2005, Expert Syst. Appl..

[8]  Garold D. Oberlender,et al.  Automated contract time determination system for highway projects , 2009 .

[9]  Khaled El-Rayes,et al.  Impact of Rainfall on the Productivity of Highway Construction , 2001 .

[10]  James T. O'Connor,et al.  Crew Production Rates for Contract Time Estimation: Bent Footing, Column, and Cap of Highway Bridges , 2005 .

[11]  Wai Kiong Oswald Chong Construction production rate information system for highway projects , 2005 .

[12]  Simon Smith,et al.  Earthmoving productivity estimation using linear regression techniques , 1999 .

[13]  G. W. Snedecor STATISTICAL METHODS , 1967 .

[14]  John Christian,et al.  Effects of Delay Times on Production Rates in Construction , 1995 .

[15]  Miroslaw J. Skibniewski,et al.  Estimating construction productivity: neural-network-based approach , 1994 .

[16]  W D McFarland,et al.  Construction contract time determination , 1992 .

[17]  R Ellis,et al.  DETERMINATION OF CONTRACT TIME FOR HIGHWAY CONSTRUCTION PROJECTS , 1995 .

[18]  Yi Jiang,et al.  Production Rates of Highway Construction Activities , 2007 .