Robust optimization models for project scheduling with resource availability cost

We address a project scheduling problem with resource availability cost for which the activity durations are uncertain. The problem is formulated within the robust optimization framework, where uncertainty is modeled via a set of scenarios. The proposed solution method is based on the scatter search methodology and employs advanced strategies, such as dynamic updating of the reference set, a frequency-based memory mechanism, and path relinking. A multistart heuristic was also developed and comparative results are reported. The tradeoffs for risk-averse decision makers are discussed.

[1]  U. Dorndorf,et al.  A Time-Oriented Branch-and-Bound Algorithm for Resource-Constrained Project Scheduling with Generalised Precedence Constraints , 2000 .

[2]  Vinícius Amaral Armentano,et al.  Scatter search for project scheduling with resource availability cost , 2006, Eur. J. Oper. Res..

[3]  Pilar Tormos,et al.  An efficient multi-pass heuristic for project scheduling with constrained resources , 2003 .

[4]  Panagiotis Kouvelis,et al.  Robust scheduling to hedge against processing time uncertainty in single-stage production , 1995 .

[5]  Douglas D. Gemmill,et al.  Using tabu search to schedule activities of stochastic resource-constrained projects , 1998, Eur. J. Oper. Res..

[6]  Dimitri Golenko-Ginzburg,et al.  Stochastic network project scheduling with non-consumable limited resources , 1997 .

[7]  F. Glover HEURISTICS FOR INTEGER PROGRAMMING USING SURROGATE CONSTRAINTS , 1977 .

[8]  R. Kolisch,et al.  Heuristic algorithms for the resource-constrained project scheduling problem: classification and computational analysis , 1999 .

[9]  Manuel Laguna,et al.  Minimizing weighted tardiness of jobs with stochastic interruptions in parallel machines , 2000, Eur. J. Oper. Res..

[10]  José Luis González Velarde,et al.  A Benders-based heuristic for the robust capacitated international sourcing problem , 2004 .

[11]  M. Laguna,et al.  Applying Robust Optimization to Capacity Expansion of One Location in Telecommunications with Demand Uncertainty , 1998 .

[12]  Laureano F. Escudero,et al.  Production planning via scenario modelling , 1993, Ann. Oper. Res..

[13]  Sacramento Quintanilla,et al.  Project Scheduling with Stochastic Activity Interruptions , 1999 .

[14]  F. Radermacher Scheduling of project networks , 1985 .

[15]  Rolf H. Möhring,et al.  Resource-constrained project scheduling: Notation, classification, models, and methods , 1999, Eur. J. Oper. Res..

[16]  Rolf H. Möhring,et al.  Linear preselective policies for stochastic project scheduling , 2000, Math. Methods Oper. Res..

[17]  Han-Lin Li,et al.  A robust optimization model for stochastic logistic problems , 2000 .

[18]  Laureano F. Escudero,et al.  CORO, a modeling and an algorithmic framework for oil supply, transformation and distribution optimization under uncertainty , 1999, Eur. J. Oper. Res..

[19]  Scott A. Malcolm,et al.  Robust Optimization for Power Systems Capacity Expansion under Uncertainty , 1994 .

[20]  Alf Kimms,et al.  Optimization guided lower and upper bounds for the resource investment problem , 2001, J. Oper. Res. Soc..

[21]  Dimitri Golenko-Ginzburg,et al.  A heuristic for network project scheduling with random activity durations depending on the resource allocation , 1998 .

[22]  Rainer Kolisch,et al.  PSPLIB - A project scheduling problem library: OR Software - ORSEP Operations Research Software Exchange Program , 1997 .

[23]  Erik Demeulemeester,et al.  Resource-constrained project scheduling: A survey of recent developments , 1998, Comput. Oper. Res..

[24]  Erik Demeulemeester,et al.  Minimizing resource availability costs in time-limited project networks , 1995 .

[25]  Rainer Kolisch,et al.  Experimental evaluation of state-of-the-art heuristics for the resource-constrained project scheduling problem , 2000, Eur. J. Oper. Res..

[26]  Peter Brucker,et al.  A branch and bound algorithm for the resource-constrained project scheduling problem , 1998, Eur. J. Oper. Res..

[27]  Fred W. Glover,et al.  Principles of scatter search , 2006, Eur. J. Oper. Res..

[28]  Robert J. Vanderbei,et al.  Robust Optimization of Large-Scale Systems , 1995, Oper. Res..

[29]  Rafael Martí,et al.  Scatter Search: Diseño Básico y Estrategias avanzadas , 2002, Inteligencia Artif..

[30]  Fred W. Glover,et al.  A Template for Scatter Search and Path Relinking , 1997, Artificial Evolution.

[31]  Franz Josef Radermacher,et al.  Algorithmic approaches to preselective strategies for stochastic scheduling problems , 1983, Networks.

[32]  Erwin Pesch,et al.  A branch-and-bound algorithm for the resource-constrained project scheduling problem , 2000, Math. Methods Oper. Res..

[33]  Genaro J. Gutierrez,et al.  A robustness approach to international sourcing , 1995, Ann. Oper. Res..

[34]  Rolf H. Möhring,et al.  Minimizing Costs of Resource Requirements in Project Networks Subject to a Fixed Completion Time , 1984, Oper. Res..