Evaluation of the geological condition ahead of the tunnel face by geostatistical techniques using TBM driving data
暂无分享,去创建一个
In tunnel excavation by Tunnel Boring Machine (TBM), it is difficult to grasp the ground condition ahead of and surrounding the tunnel face because the face cannot be observed during tunnel driving. This is the reason why it has not been possible to make the best use of high-speed excavation capability of the TBM, especially in ground under complex conditions. Thus, the TBM Excavation Control System was developed to realize the accurate prediction of the geological condition ahead of and surrounding the tunnel face simultaneously with excavation. The special feature of this system is that geostatistical techniques are introduced into the data analysis using both drill logging data from pilot boring and TBM driving data obtained during excavation, in order to improve the precision of the ground mapping.