PRACTICE TO BLOW ON AND FAST TO REACH ITS OUPTUT RATE IN 450m~3 BLAST FURNACE AFTER ITS MIDDLE REPAIR

With full preparation,a reasonable schedule made and meticulous operation,No.7 blast furnace(450 m3) reached its output rate in 3 days following the blowing on after its middle repair.