Object-Oriented Scheduling for Repetitive Projects with Soft Logics

The application of network techniques of project scheduling to repetitive projects has been criticized for the inability of network techniques to help maintain work continuity. Moreover, current network techniques require a large number of activities to represent a repetitive project and presume that there is only one logical sequence. This makes schedules time consuming to develop as well as maintain. Further, the logic chosen by the planner might be far from the shortest possible duration. This paper, utilizing the soft logic sequencing principles developed by Fan et al., develops a system which provides an easy input module in addition to scheduling and work-continuity-maintenance modules. The system eases the network generation and update processes, which in turn provides the shortest possible duration logics and the start and finish dates required to maintain work continuity.

[1]  Yvan J. Beliveau,et al.  SCaRC: Space-Constrained Resource-Constrained Scheduling System , 1997 .

[2]  Tarek Hegazy,et al.  COST OPTIMIZATION IN PROJECTS WITH REPETITIVE NONSERIAL ACTIVITIES , 2001 .

[3]  James J. O'Brien,et al.  Network scheduling variations for repetitive work , 1985 .

[4]  Shlomo Selinger Construction Planning for Linear Projects , 1980 .

[5]  David W. Johnston LINEAR SCHEDULING METHOD FOR HIGHWAY CONSTRUCTION , 1981 .

[6]  Richard Neale,et al.  CPM/LOB: New Methodology to Integrate CPM and Line of Balance , 1994 .

[7]  Robert I. Carr,et al.  Planning Construction of Repetitive Building Units , 1974 .

[8]  Hyun-Soo Lee,et al.  Network Creation and Development for Repetitive-Unit Projects , 2002 .

[9]  Rehab Reda,et al.  RPM: Repetitive Project Modeling , 1990 .

[10]  Donncha Kavanagh Siren: a repetitive construction simulation model , 1985 .

[11]  Khaled A El-Rayes,et al.  Scheduling of repetitive projects with cost optimization , 1993 .

[12]  Tarun Bafna,et al.  Discussion of "Formal Development of Line-of-Balance Technique" , 1992 .

[13]  Khaled A El-Rayes,et al.  Optimizing Resource Utilization for Repetitive Construction Projects , 2001 .

[14]  James E. Diekmann,et al.  Soft Logic in Network Analysis , 1988 .

[15]  James E. Rowings,et al.  Linear Scheduling Model: Development of Controlling Activity Path , 1998 .

[16]  Jesse Liberty Visual C# 2005 - a developer's notebook , 2005 .

[17]  James J. O'Brien VPM Scheduling for High-Rise Buildings , 1975 .

[18]  Ming-Teh Wang,et al.  Development of an object-oriented scheduling model for construction projects , 2003 .

[19]  Leen S. Kang,et al.  Optimal Schedule Planning for Multiple, Repetitive Construction Process , 2001 .

[20]  Simaan M. AbouRizk,et al.  PROBABILISTIC SIMULATION STUDIES FOR REPETITIVE CONSTRUCTION PROCESSES , 1990 .