Analysing project cost overruns: comparing the “measured mile” analysis and system dynamics modelling

Abstract The forensic analysis of failed projects is often intended to identify specific reasons and allocate blame for significant cost overruns. In claim circumstances two approaches are often used: the “measured mile”, and system dynamics simulation modelling. This note compares these approaches and argues that, although it is the most popular approach in litigation, the measured mile method is unreliable in cases where disruptions and delays are a significant part of the explanation for additional costs and late delivery of a project.

[1]  T. M. Williams,et al.  The risk of safety regulation changes in transport development projects , 1997 .

[2]  Robert Frank Cushman,et al.  Proving and Pricing Construction Claims , 1990 .

[3]  Craig A. Stephens,et al.  System Dynamics Modeling in the Legal Arena: Special Challenges of the Expert Witness Role , 2002 .

[4]  John Bowers,et al.  System dynamics in project management: a comparative analysis with traditional methods , 1996 .

[5]  Robert J. Chapman,et al.  The role of system dynamics in understanding the impact of changes to key project personnel on design production within construction projects , 1998 .

[6]  Terry Williams,et al.  Safety regulation changes during projects: the use of system dynamics to quantify the effects of change , 2000 .

[7]  Paul B. Adamsen The Rework Cycle , 2000 .

[8]  Susan Howick,et al.  The impact of disruption and delay when compressing large projects: going for incentives? , 2001, J. Oper. Res. Soc..

[9]  Fran Ackermann,et al.  Structuring a delay and disruption claim: An application of cause-mapping and system dynamics , 2003, Eur. J. Oper. Res..

[10]  Fran Ackermann,et al.  The role of feedback dynamics in disruption and delay on the nature of disruption and delay (D&D) in major projects , 2000, J. Oper. Res. Soc..

[11]  Fran Ackermann,et al.  The Effects of Design Changes and Delays on Project Costs , 1995 .

[12]  Terry Williams,et al.  Assessing Extension of Time delays on major projects , 2003 .

[13]  S. Scott Dealing with delay claims: a survey , 1993 .

[14]  Samuel B. Graves Why Costs Increase When Projects Accelerate , 1989 .

[15]  James M. Lyneis,et al.  Learning to learn, from past to future , 2002 .

[16]  Fran Ackermann,et al.  Modeling for Litigation: Mixing Qualitative and Quantitative Approaches , 1997 .

[17]  Kenneth Cooper Naval Ship Production: A Claim Settled and a Framework Built , 1980 .