Inadvertent Blowdown Event in a Nuclear Boiling Water Reactor

On March 6th 2007, the Leibstadt Nuclear Power Plant in Switzerland experienced an automatic blowdown of eight safety/relief valves installed on the main steam lines caused by a faulty electrical manipulation while performing planned maintenance during full power operation. Due to the temperature measurements inside the reactor recirculation system and the reactor pressure vessel this event, at a first glance, appeared to be Event No. 23 (Automatic Blowdown event) as an Emergency (Service Level C) Condition in accordance with the relevant reactor pressure vessel Thermal Cycle Diagram. According to the ASME Code Section III, Service Level C limits permit large deformations in areas of structural discontinuity which may necessitate the removal of a component from service for inspection or repair. This paper presents a summary of thermal-hydraulic, stress, fatigue, and fracture mechanical evaluations as well as plant inspections performed to demonstrate the impact of the event on the reactor pressure vessel and associated components and to fulfill the requirements of the Swiss Federal Nuclear Safety Inspectorate. It is shown that the primary circuit of the plant was not inadmissibly stressed by the event and that it was acceptable from a safety-related point of view to return the plant to service. Corresponding to the 7-level International Nuclear and Radiological Event Scale this event was rated afterwards as level 1 (anomaly) by the Swiss Federal Nuclear Safety Inspectorate.Copyright © 2011 by ASME