HYBRID GENETIC ALGORITHM FOR RESOURCE CONSTRAINED MULTIPROJECT SCHEDULING PROBLEM
暂无分享,去创建一个
A new hybrid genetic algorithm was proposed to solve the resource constrained multi-project scheduling problem.The algorithm utilized the serial schedule generation scheme to construct project schedules.A new chromosome was designed integrating the multi-project activity list and individual project priorities.Genetic operators,including crossover and mutation operators,ensured the next generation individuals are always precedence feasible,thus significantly accelerated the searching speed of the algorithm.A variety of heuristics and priority rules were employed to generate the original population so as to increase population diversity and avoid early constringency.A forward-backward scheduling technique was also integrated to improve the schedule quality.Results show that the algorithm can effectively allocate constraint resources to achieve a shorter overall multi-project duration.