O-cell Testings Case Histories Demonstrate the Importance of Bored Pile (Drilled Shaft) Construction Technique
暂无分享,去创建一个
Herein we review the Osterberg Cell, or O-cell, method for performing large capacity load tests on bored piles (drilled shafts), and demonstrate how it provides a new opportunity to assess the effects of construction technique. A sampling of 8 case histories, 7 with comparative testing, illustrates the impact of poor technique and thus demonstrates the importance of good construction technique. The poor techniques include inadequate bottom cleanout, failure to use drilling fluids, poor concrete placement, failure to roughen sides, and improper drilling tools. We conclude with a brief description of a recent, world record, 133 MN (15,000 tons) O-cell load test.