Perceptions towards risks involved in off-site construction in the integrated design & construction project delivery
暂无分享,去创建一个
Ruoyu Jin | Della Madgwick | Craig M. Hancock | Ping Wu | Yidong Xu | C. Hancock | Yidong Xu | R. Jin | Qingqing Lu | Ping Wu | Della Madgwick | Qingqing Lu
[1] Burcin Becerik-Gerber,et al. Understanding Construction Industry Experience and Attitudes toward Integrated Project Delivery , 2010 .
[2] Hongping Yuan,et al. A SWOT analysis of successful construction waste management , 2013 .
[3] Pramen P. Shrestha,et al. Risks Involved in Using Alternative Project Delivery (APD) Methods in Water and Wastewater Projects , 2016 .
[4] Ruoyu Jin,et al. Employees’ Safety Perceptions of Site Hazard and Accident Scenes , 2019, Journal of Construction Engineering and Management.
[5] John E. Fernández,et al. Resource Consumption of New Urban Construction in China , 2007 .
[6] Paul Slovic,et al. Perception of risk: Reflections on the psychometric paradigm , 1992 .
[7] Mustafa Alshawi,et al. BARRIERS TO INDUSTRIALIZED BUILDING SYSTEM ( IBS ) : THE CASE OF MALAYSIA , 2012 .
[8] Mehrdad Arashpour,et al. Optimal process integration architectures in off-site construction: Theorizing the use of multi-skilled resources , 2018 .
[9] Geoffrey Qiping Shen,et al. Barriers to promoting prefabricated construction in China : a cost-benefit analysis , 2018 .
[10] Ruoyu Jin,et al. An empirical study of perceptions towards construction and demolition waste recycling and reuse in China , 2017 .
[11] Nicholas Chileshe,et al. Critical success factors for implementation of risk assessment and management practices within the Tanzanian construction industry , 2014 .
[12] Jin Ouk Choi,et al. Opportunities and challenges of modular methods in dense urban environment , 2019 .
[13] Jian Zuo,et al. Offsite Manufacturing in Developing Countries: Current Situation and Opportunities , 2014 .
[14] Nicholas Chileshe,et al. A qualitative examination of major barriers in implementation of reverse logistics within the South Australian construction sector , 2016 .
[15] Seyyed Amin Terouhid,et al. Safety concerns related to modular/prefabricated building construction , 2017, International journal of injury control and safety promotion.
[16] Sun-Kyu Park,et al. An Experimental and Analytical Study on the Deflection Behavior of Precast Concrete Beams with Joints , 2017 .
[17] J. Hallikas,et al. Risk management processes in supplier networks , 2004 .
[18] Riduan Yunus,et al. Improving ecological performance of industrialized building systems in Malaysia , 2014 .
[19] Jian Zuo,et al. Barriers to the transition towards off-site construction in China: An Interpretive structural modeling approach , 2018, Journal of Cleaner Production.
[20] Poorang Piroozfar,et al. Constructing a BIM Climate–Based Framework: Regional Case Study in China , 2018, Journal of Construction Engineering and Management.
[21] Ruoyu Jin,et al. Regional Comparisons of Contemporary Construction Industry Sustainable Concepts in the Chinese Context , 2018, Sustainability.
[22] Vivian W. Y Tam,et al. Towards adoption of prefabrication in construction , 2007 .
[23] Nicholas Chileshe,et al. Risk assessment and management practices (RAMP) within the Tanzania construction industry: Implementation barriers and advocated solutions , 2014 .
[24] Geoffrey Qiping Shen,et al. Critical review of the research on the management of prefabricated construction , 2014 .
[25] Angela Lee,et al. Improving communication in managing industrialised building system (IBS) projects : virtual environment , 2018 .
[26] Chao Mao,et al. Risk factors affecting practitioners’ attitudes toward the implementation of an industrialized building system: A case study from China , 2015 .
[27] Florence Yean Yng Ling,et al. Predicting Performance of Design-Build and Design-Bid-Build Projects , 2004 .
[28] Ruidong Chang,et al. Overcoming barriers to off-site construction through engaging stakeholders: A two-mode social network analysis , 2018, Journal of Cleaner Production.
[29] H. Ross. Barriers to Implementation , 2013 .
[30] Jian Zuo,et al. A synergistic supply chain enhancing offsite manufacturing uptake in Australian house building , 2014 .
[31] P. Zou,et al. Managing Risks in Construction Projects: Life Cycle and Stakeholder Perspectives , 2009 .
[32] Xiaoling Zhang,et al. Policy risks in developing the housing product process: a holistic perspective , 2013 .
[33] Robert Eadie,et al. BIM implementation throughout the UK construction project lifecycle: An analysis , 2013 .
[34] Shang Gao,et al. A holistic review of off-site construction literature published between 2008 and 2018 , 2018, Journal of Cleaner Production.
[35] Chao Mao,et al. A SWOT analysis for promoting off-site construction under the backdrop of China’s new urbanisation , 2018 .
[36] Danny C. K. Ho,et al. Design and Build Project Success Factors: Multivariate Analysis , 2001 .
[37] Chao Mao,et al. Identification of Risk Factors Influencing the Implementation of Industrialized Building System in China , 2015 .
[38] Azrul A Mutalib,et al. Case Study to Analyse Problems and Issues in IBS Building Maintenance , 2016 .
[39] James T. O'Connor,et al. Procurement of Design-Build Services: Two-Phase Selection for Highway Projects , 2009 .
[40] M. Hosseini,et al. Critical barriers to implementing risk assessment and management practices (RAMP) in the Iranian construction sector , 2016 .
[41] Qiang Wang,et al. Exploring the relationship between urbanization, energy consumption, and CO2 emissions in different provinces of China , 2016 .
[42] Sherif Mostafa,et al. DECISION SUPPORT MODEL USING ANP TO ALIGN LEAGILE STRATEGIES TO OFF-SITE MANUFACTURING IN AUSTRALIA , 2015 .
[43] Jun Wang,et al. Cost analysis for sustainable off-site construction based on a multiple-case study in China , 2016 .
[44] L. Cronbach. Coefficient alpha and the internal structure of tests , 1951 .
[45] Abang Abdullah Abang Ali,et al. A new precast wall connection subjected to monotonic loading [Open access article] , 2016 .
[46] Mohd Nasrun Mohd Nawi,et al. READINESS ASSESSMENT FOR IMPLEMENTATION OF INTEGRATED PROJECT DELIVERY (IPD) IN INDUSTRIALISED BUILDING SYSTEM (IBS) PROJECTS , 2015 .
[47] Nicholas Chileshe,et al. Application of discrete-event simulation to investigate effects of client order behaviour on off-site manufacturing performance in Australia , 2018 .
[48] Kevin R Grosskopf,et al. Offsite construction—U.S. market trends in prefabrication , 2017 .
[49] Mehran Oraee Namzadi,et al. BIM adoption within Australian small and medium-sized enterprises (SMEs) : an innovation diffusion model , 2016 .
[50] E. Zavadskas,et al. Critical evaluation of off-site construction research: a scientometric analysis , 2018 .
[51] Willy Sher,et al. Insights into Architects’ Future Roles in Off-Site Construction , 2017 .
[52] Ruoyu Jin. Relationship between procurement duration and project performance in design-build water/wastewater projects , 2010 .
[53] A. Akintoye,et al. The allocation of risk in PPP/PFI construction projects in the UK , 2005 .
[54] Nicholas Chileshe,et al. Lean and agile integration within offsite construction using discrete event simulation : A systematic literature review , 2016 .
[55] Fabio Minghini,et al. Observational failure analysis of precast buildings after the 2012 Emilia earthquakes , 2016 .
[56] G. Norman. Likert scales, levels of measurement and the “laws” of statistics , 2010, Advances in health sciences education : theory and practice.
[57] Ruoyu Jin,et al. Study of the Relationship between Procurement Duration and Project Performance in Design-Build Projects: Comparison between Water/Wastewater and Transportation Sectors , 2013 .
[58] Angela Lee,et al. Barriers to implementation of the Industrialised Building System (IBS) in Malaysia , 2011 .
[59] M. Motiar Rahman,et al. Barriers of Implementing Modern Methods of Construction , 2014 .
[60] Heng Li,et al. Optimal single-machine batch scheduling for the manufacture, transportation and JIT assembly of precast construction with changeover costs within due dates , 2017 .
[61] Mehrdad Arashpour,et al. Assessing the Influence of Virtuality on the Effectiveness of Engineering Project Networks: “Big Five Theory” Perspective , 2018, Journal of Construction Engineering and Management.
[62] E. Chan,et al. Prefabrication and barriers to entry—a case study of public housing and institutional buildings in Hong Kong , 2006 .
[63] Nicholas Chileshe,et al. Critical factors influencing the bid/no bid decision in the Australian construction industry , 2016 .
[64] Robert F. DeVellis,et al. Scale Development: Theory and Applications. , 1992 .
[65] W. Hong,et al. Experimental investigation of the influence of steel joints upon the flexural capacity of precast concrete columns , 2017 .
[66] Seungjae Lee,et al. Verification of the Seismic Performance of a Rigidly Connected Modular System Depending on the Shape and Size of the Ceiling Bracket , 2017, Materials.
[67] Mehrdad Arashpour,et al. Critical success factors for implementing risk management systems in developing countries , 2016 .
[68] Roger J. Jiao,et al. Green modular design for material efficiency: a leader–follower joint optimization model , 2013 .
[69] Yunli Gao,et al. Constraints on the Promotion of Prefabricated Construction in China , 2018, Sustainability.
[70] Stephen O. Ogunlana,et al. Best practice of prefabrication implementation in the Hong Kong public and private sectors , 2015 .
[71] Yi Peng,et al. Exploring the challenges to industrialized residential building in China , 2014 .
[72] Timo Hartmann,et al. Yield-to-BIM: impacts of BIM maturity on project performance , 2017 .
[73] Geoffrey Qiping Shen,et al. SWOT analysis and Internet of Things-enabled platform for prefabrication housing production in Hong Kong , 2016 .
[74] Haron Ahmad Tarmizi,et al. Improving Integrated Practice through Building Information Modeling-Integrated Project Delivery (BIM-IPD) for Malaysian Industrialised Building System (IBS) Construction Projects , 2014 .
[75] Mark Konchar,et al. Comparison of U.S. Project Delivery Systems , 1998 .
[76] Shangyao Yan,et al. Optimizing profit and logistics for precast concrete production , 2017 .
[77] Mohamed Al-Hussein,et al. Construction Industrialization in China: Current Profile and the Prediction , 2017 .
[78] Tao Wang,et al. A meta-network-based risk evaluation and control method for industrialized building construction projects , 2018, Journal of Cleaner Production.
[79] A. Akintoye,et al. Risk analysis and management in construction , 1997 .
[80] Keith R. Molenaar,et al. Exploring performance of the integrated project delivery process on complex building projects , 2016 .
[81] Vivian W. Y Tam,et al. Comparing the implementation of concrete recycling in the Australian and Japanese construction industries , 2009 .
[82] Rocco J. Perla,et al. Resolving the 50‐year debate around using and misusing Likert scales , 2008, Medical education.
[83] Wei Pan,et al. Major Barriers to Off-Site Construction: The Developer’s Perspective in China , 2015 .
[84] Shoujian Zhang,et al. Effect of stakeholder collaborative management on off-site construction cost performance , 2018 .