The connection of one large power station to the main grid

The authors compare the methods used by EDF, ENEL and CEGB for the connection of one large power station to the main system. Two major issues are discussed: the principles of planning and site selection, and the connection of the new station to the main grid. For each utility the authors discuss the procedures used for siting, grid connection which includes power export considerations and security of supply to the auxiliaries. An example is given for each utility.