Investigation, modelling and planning of stochastic concrete placing operations

The concrete delivery and pumping process is a stochastic system. If analysed deterministically there is the danger that the negative effects of the random distribution of events are not taken into account, leading to poor estimates of production and cost. By representing the system as a random process the construction engineer can firstly achieve improved estimates of the overall productivity and thus schedule deliveries better, and secondly, determine the effect of non-anticipated events such as excessive delivery or pour times. This research is centred on studies of actual construction projects, which are used to study cyclic processes in general, and concreting placing operations in particular. The dataset used was gathered from over 345 concrete pours, and represents one of the largest of its type. This dataset was used as a basis for the modelling of concreting operations. These models were developed and analysed using a number of techniques, notably lean construction principles, multiple regression analysis and Monte Carlo simulation. The outcome of this research is a better understanding of how cyclic construction processes are managed and planned at a grass roots level. Firstly, by applying lean construction theories to concrete operations in the UK it was found that many are being carried out with an unacceptable amount of wasteful activities. By understanding lean construction principles some headway can be made to ensure that in future this waste is not only understood but also eliminated. Secondly, a multiple regression analysis was carried out with excellent results. Not only was it possible to identify those factors that most effect the performance of concrete placing, but also a model was developed that allows planners and engineers alike to accurately predict key responses such as pour duration and expected productivity. Finally, a simulation analysis was carried out which highlighted how the overall process reacted to changes in key times such as pump, interarrival and waiting time on site. By knowing how the process behaves and reacts to change it is possible to calculate the optimum operating conditions.

[1]  Simon Smith CONCRETE PLACING ANALYSIS USING DISCRETE-EVENT SIMULATION , 1998 .

[2]  M. Anson,et al.  Concrete pumping in the UK and West Germany: a comparison , 1989 .

[3]  David G. Carmichael,et al.  Eriang loading models in earthmoving , 1986 .

[4]  Ron Wakefield,et al.  PETRI NETS FOR SIMULATION AND MODELING OF CONSTRUCTION SYSTEMS , 1997 .

[5]  Simon Smith,et al.  Discrete-Event Simulation Analysis Of The Current UK Concrete Delivery And Placement Process – A Tool For Planners , 2002 .

[6]  Lauri Koskela,et al.  Application of the New Production Philosophy to Construction , 1992 .

[7]  Simon D. Smith,et al.  SIMULATION ANALYSIS OF THE UK CONCRETE DELIVERY AND PLACEMENT PROCESS – : A TOOL FOR PLANNERS , 2005 .

[8]  Daniel Roos,et al.  The machine that changed the world : the story of lean production , 1991 .

[9]  Simon Smith,et al.  Modelling and experimentation of the concrete supply and delivery process , 1999 .

[10]  John Christian,et al.  Effects of Delay Times on Production Rates in Construction , 1995 .

[11]  Iris D. Tommelein Discrete-Event Simulation of Lean Construction Processes , 1997 .

[12]  Richard H. Neale,et al.  Design and development of a KBES for planning and scheduling ready-mixed concrete supply , 1994 .

[13]  Michael Forde,et al.  Analysis of earth-moving systems using discrete-event simulation , 1995 .

[14]  G. Geoffrey Vining,et al.  Applied Statistics for Engineers and Physical Scientists (2nd ed.). , 1993 .

[15]  Lauri Koskela,et al.  An exploration towards a production theory and its application to construction , 2000 .

[16]  Michael Forde,et al.  THE USE OF A DISCRETE-EVENT SIMULATION MODEL WITH ERLANG PROBABILITY DISTRIBUTIONS IN THE ESTIMATION OF EARTHMOVING PRODUCTION , 1996 .

[17]  Simon Smith,et al.  Earthmoving productivity estimation using linear regression techniques , 1999 .

[18]  Simon Smith,et al.  Stochastic modelling of concrete operations , 2000 .

[19]  Iris D. Tommelein,et al.  Just-in-Time Concrete Delivery: Mapping Alternatives for Vertical Supply Chain Integration , 1999 .

[20]  Zohar J. Herbsman,et al.  Research of factors influencing construction productivity , 1990 .

[21]  Jeffrey Alun Jones,et al.  The use of a discrete event simulation to model the achievement of maintenance free operating time for aerospace systems , 2001, Annual Reliability and Maintainability Symposium. 2001 Proceedings. International Symposium on Product Quality and Integrity (Cat. No.01CH37179).

[22]  David G. Carmichael Engineering queues in construction and mining , 1987 .

[23]  ShouQing Wang,et al.  PERFORMANCE OF CONCRETE PLACING IN HONG KONG BUILDINGS , 1998 .