A practical approach to project scheduling: considering the potential quality loss cost in the time–cost tradeoff problem

Abstract Crashing project activities is a typical way to shorten their completion times to meet project due dates, and previous research on quality in time–cost tradeoff problems focused on maximizing the individual activity quality of projects. However, implementing project scheduling that takes into account the potential quality loss cost (PQLC) in time–cost tradeoff problems is a practical approach, since individual activity quality is defined by conformance to project contractor requirements. We propose a mixed integer linear programming model that considers the PQLC for excessive crashing activities. This model will help project planners develop practical project schedules.

[1]  W. L. Meyer,et al.  Extensions of the critical path method through the application of integer programming , 1963 .

[2]  M. Dessouky,et al.  Solving the Project Time/Cost Tradeoff Problem Using the Minimal Cut Concept , 1977 .

[3]  S. K. Goyal Note---A Note on “A Simple CPM Time-Cost Tradeoff Algorithm” , 1975 .

[4]  Do Ba Khang,et al.  Time, cost and quality trade-off in project management: a case study , 1999 .

[5]  Prem Vrat,et al.  A goal programming model for project crashing with piecewise linear time-cost trade-off , 1986 .

[6]  John Wateridge,et al.  How can IS/IT projects be measured for success? , 1998 .

[7]  James H. Patterson,et al.  A Horizon-Varying, Zero-One Approach to Project Scheduling , 1974 .

[8]  Srinivas Talluri,et al.  Faster, better, cheaper: A study of NPD project efficiency and performance tradeoffs , 2006 .

[9]  Erik Demeulemeester,et al.  Optimal procedures for the discrete time/cost trade-off problem in project networks , 1996 .

[10]  Mario Vanhoucke,et al.  The discrete time/cost trade-off problem: extensions and heuristic procedures , 2007, J. Sched..

[11]  G. Lieberman,et al.  Introduction to Mathematical Programming , 1990 .

[12]  Jerome D Wiest,et al.  THE SCHEDULING OF LARGE PROJECTS WITH LIMITED RESOURCES , 1962 .

[13]  Hamed R. Tareghian,et al.  A solution procedure for the discrete time, cost and quality tradeoff problem using electromagnetic scatter search , 2007, Appl. Math. Comput..

[14]  Hamed R. Tareghian,et al.  On the discrete time, cost and quality trade-off problem , 2006, Appl. Math. Comput..

[15]  Roger Atkinson,et al.  Project management: cost, time and quality, two best guesses and a phenomenon, its time to accept other success criteria , 1999 .

[16]  Wang Cheng-en,et al.  A multi-mode resource-constrained discrete time–cost tradeoff problem and its genetic algorithm based solution , 2009 .

[17]  J. D. Wiest,et al.  Management Guide to PERT/CPM , 1969 .

[18]  Christoph Schwindt,et al.  Resource allocation in project management , 2005 .

[19]  Walter O. Rom,et al.  Ensuring quality in resource constrained project scheduling , 1997 .

[20]  Peter Brucker,et al.  Complex Scheduling , 2006 .

[21]  D. R. Robinson A Dynamic Programming Solution to Cost-Time Tradeoff for CPM , 1975 .

[22]  Chung-Wei Feng,et al.  Using genetic algorithms to solve construction time-cost trade-off problems , 1997 .

[23]  Nicolai Siemens A Simple CPM Time-Cost Tradeoff Algorithm , 1971 .

[24]  Sadi Assaf,et al.  Causes of delay in large construction projects , 2006 .

[25]  Srilal Perera Linear Programming Solution to Network Compression , 1980 .

[26]  W. Verdini,et al.  Nonlinear time/cost tradeoff models in project management , 1995 .

[27]  Nalina Suresh,et al.  Project management with time, cost, and quality considerations , 1996 .

[28]  Jean Couillard,et al.  Assessing and controlling the quality of a project end product: the earned quality method , 2000, IEEE Trans. Engineering Management.

[29]  D. R. Fulkerson A Network Flow Computation for Project Cost Curves , 1961 .

[30]  James E. Kelley,et al.  Critical-Path Planning and Scheduling: Mathematical Basis , 1961 .

[31]  Christina M. Scott-Young,et al.  Project success and project team management: Evidence from capital projects in the process industries , 2008 .

[32]  R. E. Cooke-Yarborough,et al.  Critical Path Planning and Scheduling: An Introduction and Example , 1964 .

[33]  A. Chakrabarti,et al.  Speeding Up the Pace of New Product Development , 1999 .

[34]  Nigel J. Smith,et al.  Application of a fuzzy based decision making methodology to construction project risk assessment , 2007 .

[35]  Karen Tate,et al.  Getting Started in Project Management , 2001 .

[36]  David I. Cleland,et al.  Matrix Management Systems Handbook , 1984 .

[37]  Athanasios P. Chassiakos,et al.  Project time-cost analysis under generalised precedence relations , 2002 .