THE METHOD FOR IMPROVING STABILITY OF CONSTRUCTION PROJECT SCHEDULES THROUGH BUFFER ALLOCATION / STATYBOS VYKDYMO GRAFIKO STABILUMO UŽTIKRINIMAS PASKIRSTANT LAIKO REZERVUS

Abstract. The actual completion time of construction projects is rarely in accordance with initial plans. This is due to unforeseen events that affect the project execution. In the paper, the authors propose a method of improving the construction schedule reliability. The method is based on the idea of buffers allocation, whose proper sizing helps to reduce negative effects of random conditions on the progress and efficiency of project activities. The authors adopt a proactive approach to the construction of robust schedules to cope with multiple disruptions during project execution, applicable to two processes starting policies (as soon as possible or no sooner than on a predefined date). The proposed method, based on simulation technique and mathematical programming, was illustrated by an example. The results obtained by means of the proposed method were compared, in terms of schedule stability, to those of the float factor heuristic and starting time criticality heuristic procedures. The method allowed...

[1]  Sławomir Biruk,et al.  The work continuity constraints problem in construction projects' network models , 2009 .

[2]  Bao Xi,et al.  The uncertainty evaluation method of supply chain reliability , 2009 .

[3]  Khaled Nassar,et al.  Analysis of timed petri nets for reachability in construction applications , 2008 .

[4]  Sławomir Biruk,et al.  Simulation modelling construction project with repetitive tasks using Petri nets theory , 2008 .

[5]  Oleg Kapliński,et al.  Three phases of multifactor modelling of construction processes , 2006 .

[6]  Oleg Kapliński,et al.  Development and usefulness of planning techniques and decision‐making foundations on the example of construction enterprises in Poland , 2008 .

[7]  Lindu Zhao,et al.  A Game Theoretic Optimization Model between Project Risk Set and Measure Set , 2009, Int. J. Inf. Technol. Decis. Mak..

[8]  Dorota Kuchta,et al.  Use of fuzzy numbers in project risk (criticality) assessment , 2001 .

[9]  Raufdeen Rameezdeen,et al.  Risk management in road construction: The case of Sri Lanka , 2009 .

[10]  Feniosky Peña-Mora,et al.  Reliability Buffering for Construction Projects , 2004 .

[11]  Symeon E. Christodoulou Construction imitating ants: Resource-unconstrained scheduling with artificial ants , 2009 .

[12]  Cengiz Kahraman,et al.  Investment analyses using fuzzy probability concept , 2010 .

[13]  Jerzy Pasławski,et al.  Monitoring of construction processes in the variable environment , 2008 .

[14]  Martin Schieg,et al.  Strategies for Avoiding Asymmetric Information in Construction Project Management , 2008 .

[15]  Romualdas Ginevičius,et al.  Selection of the optimal real estate investment project basing on multiple criteria evaluation using stochastic dimensions , 2009 .

[16]  Erik Demeulemeester,et al.  The use of buffers in project management: The trade-off between stability and makespan , 2004 .

[17]  Oleg Kapliński,et al.  Information technology in the development of the Polish construction industry , 2009 .

[18]  Willy Herroelen,et al.  The construction of stable project baseline schedules , 2004, Eur. J. Oper. Res..

[19]  R. Leus,et al.  The trade-off between stability and makespan in resource-constrained project scheduling , 2004 .

[20]  Shu-Shun Liu,et al.  Resource-constrained construction project scheduling model for profit maximization considering cash flow , 2008 .

[21]  Irene Lill,et al.  Multiskilling in Construction – A Strategy for Stable Employment , 2009 .

[22]  Yakov Ben-Haim,et al.  ROBUST RELIABILITY OF PROJECTS WITH ACTIVITY-DURATION UNCERTAINTY , 1998 .

[23]  Mohamed Haouari,et al.  A bi-objective model for robust resource-constrained project scheduling , 2005 .

[24]  Tomasz Błaszczyk,et al.  The time‐cost trade‐off analysis in construction project using computer simulation and interactive procedure , 2009 .

[25]  Leonas Ustinovichius,et al.  Multi‐attribute analysis of investments risk alternatives in construction , 2008 .

[26]  Sherif Ali Mohtady Mohamed,et al.  Factors affecting the performance of construction projects in the Gaza Strip , 2009 .

[27]  Amir Saman Kheirkhah,et al.  Developing Strategies to Reduce the Risk of Hazardous Materials Transportation in Iran Using the Method of Fuzzy SWOT Analysis , 2009 .

[28]  Oleg Kapliński,et al.  Game theory applications in construction engineering and management , 2010 .

[29]  Luís Valadares Tavares,et al.  On the optimal management of project risk , 1998, Eur. J. Oper. Res..

[30]  Edmundas Kazimieras Zavadskas,et al.  Risk assessment of construction projects , 2010 .

[31]  Dorota Kuchta,et al.  A note on the paper by M. A. Al-Fawzan and M. Haouari about a bi-objective problem for robust resource-constrained project scheduling , 2007 .

[32]  Jerzy Pasławski,et al.  Flexibility approach in construction process engineering , 2008 .

[33]  Oleg Kapliński Guest editorial: Planning instruments in construction management , 2008 .

[34]  Kasthurirangan Gopalakrishnan,et al.  Neural networks surrogate models for simulating payment risk in pavement construction , 2008 .

[35]  Friedel Peldschus,et al.  Experience of the game theory application in construction management , 2008 .

[36]  Piotr Jaśkowski,et al.  Scheduling Construction Projects Using Evolutionary Algorithm , 2006 .

[37]  Erik Demeulemeester,et al.  Proactive heuristic procedures for robust project scheduling: An experimental analysis , 2008, Eur. J. Oper. Res..

[38]  Henri Pierreval,et al.  Analysis of robustness in proactive scheduling: A graphical approach , 2010, Comput. Ind. Eng..