Forensic project management: The underlying causes of rework in construction projects

Construction professionals recognize that rework is a significant factor contributing to poor project performance, yet little is known about its antecedents and consequently it remains an innate problem. Because factors that contribute to its occurrence are not fully understood, the derivation of appropriate strategies for its reduction is problematic. Therefore, a comprehensive appreciation of the mechanisms that cause rework will enable project performance improvements to be made. Two longitudinal case studies were undertaken to determine the antecedents of rework. Based on the findings presented, strategies for reducing the incidence of rework are identified and discussed. This paper contributes to study of quality in construction by identifying the underlying factors that influence rework in projects.

[1]  T. Hillman Willis,et al.  A quality performance management system for industrial construction engineering projects , 1996 .

[2]  Gregory A. Howell,et al.  Interaction between subcycles: one key to improved methods , 1993 .

[3]  David Picken,et al.  The effect on contingency allowances of using risk analysis in capital cost estimating: a Hong Kong case study , 1998 .

[4]  Peter E.D. Love,et al.  Influence of Project Type and Procurement Method on Rework Costs in Building Construction Projects , 2002 .

[5]  Mike Hoxley,et al.  Are competitive fee tendering and construction professional service quality mutually exclusive? , 2000 .

[6]  Gregory A. Howell,et al.  SHIELDING PRODUCTION: ESSENTIAL STEP IN PRODUCTION CONTROL , 1998 .

[7]  Lauri Koskela,et al.  An exploration towards a production theory and its application to construction , 2000 .

[8]  Peter E.D. Love,et al.  Some empirical observations of service quality in construction , 2000 .

[9]  Geoff Rounce Quality, waste and cost considerations in architectural building design management , 1998 .

[10]  Peter E.D. Love,et al.  Quantifying the causes and costs of rework in construction , 2000 .

[11]  Arthur A. Defraites Fee versus Quality , 1989 .

[12]  W. H. Harrison,et al.  An investigation into faults and their avoidance , 1982 .

[13]  A. Sohal,et al.  Capturing rework costs in projects , 2003 .

[14]  Peter E.D. Love,et al.  The propagation of rework benchmark metrics for construction , 1999 .

[15]  John S. Oakland,et al.  Quality management in civil and structural engineering consulting , 1995 .

[16]  Will Hughes,et al.  Building Design Management , 2001 .

[17]  Jim Smith,et al.  Digital simulation of option-choice behaviour , 2000 .

[18]  Ali Jaafari,et al.  Human Factors in the Australian Construction Industry: Towards Total Quality Management , 1996 .

[19]  Robert J. Chapman,et al.  The effectiveness of working group risk identification and assessment techniques , 1998 .

[20]  B. Hollins,et al.  Design in the service sector , 1993 .

[21]  Mohammad Mahmoud Abolnour The relationship of fee structure in engineering offices and design deficiency , 1994 .

[22]  W. B. Ledbetter,et al.  Causes of Quality Deviations in Design and Construction , 1992 .

[23]  C Eden,et al.  Mapping distinctive competencies: a systemic approach , 2000, J. Oper. Res. Soc..

[24]  Sadi Assaf,et al.  Quality practices in design organizations , 1999 .

[25]  Albert P. C. Chan Quality Assurance in the Construction Industry , 1996 .

[26]  David Picken,et al.  Using Risk Analysis to Determine Construction Project Contingencies , 2000 .

[27]  기술전략팀 [기술강좌] Last Planner , 2003 .

[28]  Peter E.D. Love,et al.  Auditing the indirect consequences of rework in construction: a case based approach , 2002 .

[29]  Christopher Powell Responding to marginalisation , 1997, Architectural Research Quarterly.

[30]  Peter E.D. Love,et al.  Determining the causal structure of rework influences in construction , 1999 .

[31]  Nikkan Kogyo Shimbun Poka-Yoke : Improving Product Quality by Preventing Defects , 1989 .

[32]  Fran Ackermann,et al.  Modeling for Litigation: Mixing Qualitative and Quantitative Approaches , 1997 .

[33]  P. Love,et al.  Rework: a symptom of a dysfunctional supply-chain , 1999 .

[34]  John Gardiner Management of Design Documentation Where Do We Go from Here , 1994 .

[35]  Jodi J. Farrington,et al.  A Methodology to Identify and Categorize Costs of Quality Deviations in Design and Construction , 1987 .

[36]  Karl-Olof Nylén,et al.  Cost of failure in a major civil engineering project , 1996 .

[37]  J. L. Ashford,et al.  The Management of Quality in Construction , 2002 .

[38]  Alphonse J. Dell'Isola,et al.  Value engineering : practical applications --for design, construction, maintenance & operations , 1997 .

[39]  Chimay J. Anumba,et al.  CONCURRENT ENGINEERING : Research and Applications Client Requirements Processing for Concurrent Life-Cycle Design and Construction , 2006 .

[40]  Andrew D. Seidel,et al.  Architects and their practices : a changing profession , 1995 .

[41]  Fran Ackermann,et al.  The role of feedback dynamics in disruption and delay on the nature of disruption and delay (D&D) in major projects , 2000, J. Oper. Res. Soc..

[42]  C. Tomkins,et al.  Quality failure costs in civil engineering projects , 2000 .

[43]  Glenn Ballard,et al.  Lean construction and EPC performance improvement , 1997 .

[44]  Geoff Conroy,et al.  ConSERV, a project specific risk management concept , 1998 .

[45]  Per-Erik Josephson,et al.  Illustrative Benchmarking Rework and Rework Costs in Swedish Construction Industry , 2002 .

[46]  Vernon February The Many Voices of the Land , 1996 .

[47]  Landon C.G. Miller Concurrent Engineering Design: Integrating the Best Practices for Process Improvement , 1993 .

[48]  Barrie Dale,et al.  The Management of Quality:: A Top Management View , 1984 .

[49]  P.-E Josephson,et al.  The causes and costs of defects in construction. A study of seven building projects , 1999 .

[50]  John G. Perry,et al.  Limitation of design liability for contractors , 1999 .

[51]  Brian Richardson,et al.  Marketing for Architects and Engineers: A new approach , 1996 .

[52]  Tetsuichi Asaka,et al.  Handbook of Quality Tools: The Japanese Approach , 1996 .

[53]  Bryan Lawson,et al.  How Designers Think: The Design Process Demystified , 1990 .

[54]  Peter E.D. Love,et al.  Triangulation in construction management research , 2002 .

[55]  Diane H. Sonnenwald,et al.  Communication roles that support collaboration during the design process , 1996 .

[56]  John S. Oakland,et al.  Total Quality Management: Text with Cases , 1995 .