FIRST RF TESTS IN THE HOBICAT SUPERCONDUCTING TEST FACILITY AT BESSY

In preparation for the construction of the BESSY-FEL User Facility, BESSY recently completed the installation of the HoBiCaT cryogenic test facility for superconducting RF (SRF) TESLA cavity units [1], including all ancillary devices (helium tank, input coupler, tuner, magnetic shielding). It is designed to house two such units in a configuration similar to that envisaged for the superconducting CW linac of the BESSY FEL. Commissioning of the facility is now complete and the first TTF-III RF coupler and cavity unit has been tested. In particular, the complete production, cleaning and assembly of the cavity unit was carried out by industry. These tests thus serve as a first step at qualifying industrial partners for series production of such systems, which will be essential for the future construction of SRF based light sources.