Tunneling with full face shielded machines: A study on the backfilling of the tail void

In mechanized tunneling the annular gap between the segmental lining and the surrounding soil caused by tunnel driving, must be backfilled almost instantaneously with an adequate grouting mortar. The objective of this research is to perform a fully three dimensional modeled parametric study using FLAC 3D and evaluate the effects of backfill grouting on the tunneling performance. The research focuses on comparisons between different injection materials and state-of-the-art Bi-Component grout and their effects on the settlements on the surface. The research consists of testing a regular situation of tunnel excavation using a shielded machine with face under pressure. The tunnel dimensions and the soil properties are selected as close as possible to the reality and based on Turin Metro case.