Risk management applicable to shield TBM tunnel: II. Risk analysis methodology

In this paper, a risk analysis methodology applicable to shield TBM tunnels was studied. Fault Tree Analysis (FTA) was utilized to identify all risk items and to calculate the probability of failure of each item and Analytic Hierarchy Process (AHP) was used to obtain the impact of each risk item. Finally, a risk level of each risk item can be assessed. Developed methodology is applied to a Seoul subway site in which EPB shield tunnel method was utilized and it was found that risk analysis results matched reasonably well with field data.