SIMULATION METHOD OF CONSTRUCTION HOIST OPERATING PLAN FOR HIGH RISE BUILDINGS CONSIDERING LIFTING HEIGHTS AND LOADS

Lifting indicates vertical transfer of construction resources. In high-rise building, efficient plan and management on lifting of resources are ess ential because of enormous impact on schedule, and amount of resources and data. In part icular, a hoist—one of main lifting equipment for workers and construction materials—may have direct influence on overall project schedule depending on its number, location and operation method. To ensure efficient construction, it is critical to have an optimal hoi st operating plan. Engineers depend on various empirical methods, which have been optimized through numerous feedbacks from construction projects. Therefore, it is necessary t o optimize hoist plan and management based on both engineers’ experiences and simulation based on actual data on lifting load and height. This paper describes a simulation method to provide data to an experienced engineer for accurate decision-making.